PM1 Unit 5 Review

PM1 Unit 5 Review

Assessment

Flashcard

Business

9th - 12th Grade

Hard

Created by

Quizizz Content

FREE Resource

Student preview

quiz-placeholder

21 questions

Show all answers

1.

FLASHCARD QUESTION

Front

Mary is using which tool to manage the cost of this project?

Back

funding limit reconciliation

2.

FLASHCARD QUESTION

Front

Liz looks at the activity costs that must be incurred to complete all project deliverables. Liz is determining the:

Back

project funding requirements.

3.

FLASHCARD QUESTION

Front

Felicia averages three quoted costs and determines that she will need to put an extra $20,000 into the project budget. What cost estimating technique did Felicia use?

Back

vendor bid analysis

4.

FLASHCARD QUESTION

Front

What is the project's earned value if it has a budget of $1,500, is 40% complete, and Hollie planned to spend $500 a month?

Back

$600

5.

FLASHCARD QUESTION

Front

Glenn is determining the project cost baseline by calculating the costs approved for each of the project's work packages. Glenn is determining the:

Back

planned value.

6.

FLASHCARD QUESTION

Front

The project manager would like to show the rate at which the project is progressing compared to what was planned. What indicator should she reference?

Back

schedule performance index

7.

FLASHCARD QUESTION

Front

The project manager would like to determine the aggregate estimated costs from the individual work packages to create a detailed breakdown of projected costs. In which process is the project manager most likely participating?

Back

determine budget

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?