Mastering Time and Work Concepts

Mastering Time and Work Concepts

Professional Development

20 Qs

quiz-placeholder

Similar activities

2nd periodical Math6

2nd periodical Math6

1st Grade - Professional Development

20 Qs

Team Test - Time & Work , Chain Rule , Pipes & Cistern

Team Test - Time & Work , Chain Rule , Pipes & Cistern

Professional Development

15 Qs

Learning Test - Time & Work,Chain Rule,Pipes &  Cisturn

Learning Test - Time & Work,Chain Rule,Pipes & Cisturn

Professional Development

15 Qs

ATTRC SPEED TEST MATH

ATTRC SPEED TEST MATH

Professional Development

20 Qs

stuff

stuff

5th Grade - Professional Development

15 Qs

WEEK 2 GMAT QUANTITATIVE

WEEK 2 GMAT QUANTITATIVE

Professional Development

21 Qs

aptitude

aptitude

Professional Development

15 Qs

ISC2020 ZIET,BBSR 2ND SPELL MID TEST

ISC2020 ZIET,BBSR 2ND SPELL MID TEST

Professional Development

20 Qs

Mastering Time and Work Concepts

Mastering Time and Work Concepts

Assessment

Quiz

Mathematics

Professional Development

Hard

Created by

Shithu Lal

Used 5+ times

FREE Resource

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

If A can complete a work in 10 days and B in 15 days, how long will they take to complete it together?

6 days

8 days

5 days

12 days

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A can do a piece of work in 12 days, while B can do it in 18 days. How long will they take to finish the work together?

10 days

5 days

7.2 days

8 days

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

If A works twice as fast as B and they complete a job in 6 days together, how long would A take to complete the job alone?

15 days

12 days

3 days

9 days

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A can finish a task in 20 days, B in 30 days, and C in 60 days. How long will it take for all three to complete the task together?

15 days

25 days

5 days

10 days

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

If A and B can complete a work in 8 days, and A alone can do it in 12 days, how long will B take to complete the work alone?

24 days

20 days

16 days

30 days

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A can complete a job in 15 days, B in 10 days, and C in 5 days. What is the ratio of their work rates?

1:2:3

3:4:5

4:5:6

2:3:6

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

If A can do a job in 24 hours and B can do it in 36 hours, how long will it take them to complete the job together?

18 hours

20 hours

12 hours

14.4 hours

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?