Mastering Time and Work Concepts

Mastering Time and Work Concepts

Professional Development

20 Qs

quiz-placeholder

Similar activities

QSM8 - Numérico-Abstracto_Clase demostrativa N°6

QSM8 - Numérico-Abstracto_Clase demostrativa N°6

University - Professional Development

15 Qs

GCSE maths quiz based on UK COVID status at 7 Jan 2020.

GCSE maths quiz based on UK COVID status at 7 Jan 2020.

Professional Development

20 Qs

1dnl MIF Pascal's triangle

1dnl MIF Pascal's triangle

12th Grade - Professional Development

17 Qs

YR6 比与比例(2/12/2020)

YR6 比与比例(2/12/2020)

Professional Development

20 Qs

Diskusi Executive TIU bersama Kak Noer

Diskusi Executive TIU bersama Kak Noer

Professional Development

15 Qs

TRY OUT SKD MBC

TRY OUT SKD MBC

Professional Development

20 Qs

Significant Figures and Rounding

Significant Figures and Rounding

Professional Development

20 Qs

QUIZ SCM 300 WEEK 3

QUIZ SCM 300 WEEK 3

KG - Professional Development

15 Qs

Mastering Time and Work Concepts

Mastering Time and Work Concepts

Assessment

Quiz

Mathematics

Professional Development

Practice Problem

Hard

Created by

Shithu Lal

Used 5+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

If A can complete a work in 10 days and B in 15 days, how long will they take to complete it together?

6 days

8 days

5 days

12 days

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A can do a piece of work in 12 days, while B can do it in 18 days. How long will they take to finish the work together?

10 days

5 days

7.2 days

8 days

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

If A works twice as fast as B and they complete a job in 6 days together, how long would A take to complete the job alone?

15 days

12 days

3 days

9 days

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A can finish a task in 20 days, B in 30 days, and C in 60 days. How long will it take for all three to complete the task together?

15 days

25 days

5 days

10 days

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

If A and B can complete a work in 8 days, and A alone can do it in 12 days, how long will B take to complete the work alone?

24 days

20 days

16 days

30 days

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A can complete a job in 15 days, B in 10 days, and C in 5 days. What is the ratio of their work rates?

1:2:3

3:4:5

4:5:6

2:3:6

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

If A can do a job in 24 hours and B can do it in 36 hours, how long will it take them to complete the job together?

18 hours

20 hours

12 hours

14.4 hours

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?