Cold Water - Mock 2

Cold Water - Mock 2

12th Grade

45 Qs

quiz-placeholder

Similar activities

9189PH2CW2

9189PH2CW2

12th Grade

50 Qs

Feed and Expansion Cistern Quiz

Feed and Expansion Cistern Quiz

12th Grade

50 Qs

Quiz on Gas Laws and Water Boiling Point

Quiz on Gas Laws and Water Boiling Point

12th Grade

49 Qs

Sistem EFI

Sistem EFI

12th Grade - University

40 Qs

UAS PMKR KELAS XII

UAS PMKR KELAS XII

12th Grade

50 Qs

Types and Layout Features of Systems Quiz

Types and Layout Features of Systems Quiz

12th Grade

41 Qs

unit 113 heating part 1

unit 113 heating part 1

12th Grade

43 Qs

Environmental

Environmental

12th Grade

50 Qs

Cold Water - Mock 2

Cold Water - Mock 2

Assessment

Quiz

Other

12th Grade

Hard

Created by

Adam Dreifuss

Used 3+ times

FREE Resource

45 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The legal requirements for the installation of cold water services are stated in the

British Standards

Building Regulations

Water Regulations

Construction Regulations

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

To establish whether a cold water supply to a dwelling is adequate to feed all the plumbing appliances, the best item of equipment to use is a

water meter

manometer

flow meter

air test gauge

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A plumbing operative identifies that a low pressure cold water system does not provide a suitable flow rate to an electric shower, supplied by the plumbing company, that is to be installed. Who should be the first point of contact?

Water company

Local authority

Customer

Supervisor

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which one of the following is approved for use on underground service pipes?

Solder fittings with lead / tin solder

Push fit plastic fittings

Type ‘B’ compression fittings

Type ‘A’ compression fittings

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The Water Regulations state that the minimum permissible distance from the external wall of a dwelling, to where an uninsulated service pipe enters the inside of the building, is

150 mm

250 mm

550 mm

750 mm

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The last isolation valve on a supply pipe to a cold water storage cistern is the

float operated valve

draining valve

servicing valve

supply stop valve

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The recommended clip spacing for a vertical cold water service pipe in 15 mm copper is

1.0 m

1.3 m

1.5 m

1.8 m

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?