1.

MULTIPLE SELECT QUESTION

30 sec • 1 pt

Transparency Requirement for Procuring Entities, check all that applies:

Downloadable complete bidding documents in Procuring Entity's website

Notice to Proceed in a Conspicuous Place

Project Procurement Management Plan (PPMP) in the Procuring Entity's website

Approved Contract in the PhilGEPS website

Answer explanation

Notice to Proceed is not required to be posted in Conspicuous Places, only up to the Notice of Award

Rather than PPMP, the Annual Procurement Plan (APP) is required to be posted in the Agency's Transparency Seal (found in the website)

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Pre-bid Conference is required for procurement projects ____________

With ABC equal to or more than 1,000,000

Where a supplier with Red membership is involved

Where an Asset (Capital Outlay) is involved

Where the mode of procurement is "Negotiated Procurement"

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How long should the Invitation of Bid be posted?

Seven (7) Working Days

Seven (7) Calendar Days

Fifteen (15) Working days

Fifteen (15) Calendar Days

Answer explanation

Section 21.2.1, IRR of RA 9184

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Based on the guidelines on the sale of bidding documents, how much is the maximum cost of bidding documents for Procurement Projects with ABC of 10 million

5% of ABC

Php 10,000

Php 25,000

3% of ABC

Answer explanation

Media Image

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Competitive Bidding is open to participation by any interested party and consists of the following processes, EXCEPT:

Pre-Bid Conference

Exit Conference

Opening of Bids

Eligibility Screening

Answer explanation

Every year, an exit conference is conducted between COA and the auditee to discuss audit findings and recommmendations

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

GPPB resolution No. 16-2019 and GPPB Resolution No. 09-2020 provides that _______

Procurement officers and officials may digitally or electronically sign procurement documents

Bids and Awards Committee may revise disbursement schedule of the Procurement upon recommendation of Chief Accountant

Platinum and Red membership has a grace period of thirty (30) working days for renewal

Observers are allowed to join through an online conferencing tool as long as the recording is provided to GPPB-TSO

Answer explanation

Resolution No. 16-2019

Approval of the use of digital signature in procurement related documents

Resolution No. 09-2020

Approving measures for the efficient conduct of procurement activities during a state of calamity, or implementation of community quarantine or similar restrictions

Except contract, contract has to be wet signature

7.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

For the procurement of non-expendable supplies and services, the Statement of Single Largest Completed Contract (SLCC) provides that:

A single contract that is similar to this project, equivalent to at least fifty (50%) percent of the ABC

A single contract that is similar to this project, equivalent to at least twenty-five (25%) percent of the ABC

A single contract that is similar to this project, equivalent to at least ten (10%) perfect of the ABC

A single contract that is similar to this project, equivalent to at least fifteen (15%) of the ABC

Answer explanation

50% for non expendable supplies and services

25% for expendable supplies

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?