GMJ 6035 Hot water testing and commissioning outcome 6 quiz

Authored by Glen Johnson

Construction

Vocational training

Used 22+ times

GMJ 6035 Hot water testing and commissioning outcome 6 quiz
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

21 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which step is performed first during soundness testing of domestic hot water systems?

Attach the hydraulic test bucket

Pump the system up to test pressure

Visual check of the system for joints and clips

Leave the system for temperature stabilization

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the required test pressure for rigid pipe soundness testing?

1.5 times the working pressure

2 times the working pressure

1.2 times the working pressure

1 bar above working pressure

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How long should rigid pipes be left after filling the system with water to stabilize the temperature?

15 minutes

30 minutes

1 hour

45 minutes

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

For plastic pipe (Test A), what is the initial test pressure and duration?

1 bar for 30 minutes

1.5 times working pressure for 15 minutes

1 bar for 45 minutes

2 bar for 45 minutes

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which British Standard applies to flushing and disinfecting of new domestic hot water systems?

BS EN 806

BS 6700

BS 1710

BS 8000

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the next action after adding disinfectant (chlorine solution) to a domestic hot water system?

Flush the system immediately

Leave the system with disinfectant for 30 minutes

Leave the system for 1 hour

Test pressure after disinfection

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How should the system be refilled and tested after replacing a component during temporary decommissioning?

Refill with clean water and flush

Connect to drain points and drain the system

Fill and pressure test the system

Add disinfectant and inspect all joints

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?