GMJ 6035 Hot water testing and commissioning outcome 6 quiz

GMJ 6035 Hot water testing and commissioning outcome 6 quiz

Vocational training

21 Qs

quiz-placeholder

Similar activities

305 Cold water systems 3 Quiz

305 Cold water systems 3 Quiz

2nd Grade - University

18 Qs

Year 1 Carpentry & Joinery

Year 1 Carpentry & Joinery

KG - University

17 Qs

Unidad 1: Introducción al Lean Construction

Unidad 1: Introducción al Lean Construction

University

20 Qs

C8 RADIOACTIVE

C8 RADIOACTIVE

1st - 5th Grade

20 Qs

305 Cold Water systems  2 Quiz

305 Cold Water systems 2 Quiz

2nd Grade

20 Qs

Bpec Low Carbon Steel

Bpec Low Carbon Steel

KG - University

20 Qs

Basic Electrical Construction Documents (Electrical L1) Quiz

Basic Electrical Construction Documents (Electrical L1) Quiz

12th Grade

20 Qs

SCROLL SAW QUIZ

SCROLL SAW QUIZ

9th Grade

16 Qs

GMJ 6035 Hot water testing and commissioning outcome 6 quiz

GMJ 6035 Hot water testing and commissioning outcome 6 quiz

Assessment

Quiz

Construction

Vocational training

Hard

Created by

Glen Johnson

Used 10+ times

FREE Resource

21 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which step is performed first during soundness testing of domestic hot water systems?

Attach the hydraulic test bucket

Pump the system up to test pressure

Visual check of the system for joints and clips

Leave the system for temperature stabilization

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the required test pressure for rigid pipe soundness testing?

1.5 times the working pressure

2 times the working pressure

1.2 times the working pressure

1 bar above working pressure

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How long should rigid pipes be left after filling the system with water to stabilize the temperature?

15 minutes

30 minutes

1 hour

45 minutes

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

For plastic pipe (Test A), what is the initial test pressure and duration?

1 bar for 30 minutes

1.5 times working pressure for 15 minutes

1 bar for 45 minutes

2 bar for 45 minutes

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which British Standard applies to flushing and disinfecting of new domestic hot water systems?

BS EN 806

BS 6700

BS 1710

BS 8000

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the next action after adding disinfectant (chlorine solution) to a domestic hot water system?

Flush the system immediately

Leave the system with disinfectant for 30 minutes

Leave the system for 1 hour

Test pressure after disinfection

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How should the system be refilled and tested after replacing a component during temporary decommissioning?

Refill with clean water and flush

Connect to drain points and drain the system

Fill and pressure test the system

Add disinfectant and inspect all joints

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?