DCOR 2

DCOR 2

Professional Development

8 Qs

quiz-placeholder

Similar activities

Week 4. lesson planning

Week 4. lesson planning

Professional Development

10 Qs

pelatihan guru yadika

pelatihan guru yadika

Professional Development

10 Qs

PROFIL IIS PSM KEDIRI

PROFIL IIS PSM KEDIRI

Professional Development

10 Qs

19. Juli SMK 2 Malang Deutschunterricht

19. Juli SMK 2 Malang Deutschunterricht

Professional Development

10 Qs

KUIS MGMP

KUIS MGMP

Professional Development

10 Qs

Truman Show

Truman Show

Professional Development

10 Qs

SO Upper u 7 test

SO Upper u 7 test

Professional Development

13 Qs

MODAL VERBS & ADVERBS PRACTICE

MODAL VERBS & ADVERBS PRACTICE

Professional Development

10 Qs

DCOR 2

DCOR 2

Assessment

Quiz

World Languages

Professional Development

Practice Problem

Easy

Created by

Wan Utama

Used 1+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

8 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

What is the primary objective of Implementing the COR Plan?

To ensure the approved COR Plan is executed and progress is monitored

To finalize the project financial statements

To dissolve the Project Management Team (PMT)

2.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

What should be done to ensure COR deliverables are properly integrated into the system? 

Conduct an external audit before closing the project

Store all data in ECMS to support daily plant and commercial operations

Distribute printed reports to all employees

3.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

What is the purpose of conducting a COR Implementation Review (CIR)? 

To review the plan, outcomes, and develop Project Lesson Learnt

To approve new financial budgets for the next project phase

To compare COR plan and implement the appropriate plan

4.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

What tools / documents are used for reviewing COR Implementation? 

Financial budgeting software

COR Implementation Review (CIR) template and checklist

Market analysis reports

5.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

Who is the Main Role to initiate the implementation of COR plan?

Project Manager

COR Implementer

BD Lead

COR Lead

6.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

These are the supporting role to review COR Implementation, except?

Project Sponsor

COR Implementer

COR Lead

Project Controller

7.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

Who is the supporting role in preparing the COR Closure Package? 

COR Implementer

BD Lead

COR Lead

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?