800-850 Updated

800-850 Updated

1st Grade

31 Qs

quiz-placeholder

Similar activities

PMI SH - Build and Lead a Team (0.5)

PMI SH - Build and Lead a Team (0.5)

1st Grade

30 Qs

Project Management Part 3

Project Management Part 3

1st Grade

32 Qs

Project Management Part 1

Project Management Part 1

1st Grade

30 Qs

Program Stakeholder Engagement

Program Stakeholder Engagement

1st Grade

36 Qs

Quiz8

Quiz8

1st Grade

26 Qs

601-650 Updated

601-650 Updated

1st Grade

28 Qs

400-500/1706 New

400-500/1706 New

1st - 5th Grade

31 Qs

15-16 Updated

15-16 Updated

1st - 5th Grade

31 Qs

800-850 Updated

800-850 Updated

Assessment

Quiz

Professional Development

1st Grade

Hard

Created by

Afghanistan Center

FREE Resource

31 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully What should the project manager do next?

Establish the project scope and set clear team objectives

Set performance standards and direction

Hold early kick-off meetings and regular weekly meetings

Select members for their skill or potential

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project is being delayed due to a large amount of rework caused by a quality problem that is impacting the critical path. What should the project manager do?

Rebaseline the project schedule to absorb the delay.

Report the delay with rectifying actions to the project management office (PMO).

Notify the project steering committee about the cause of the delay.

Report the delay with rectifying actions to the change control board (CCB) for review,

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project is experiencing delays due to identified risks What should the project manager do to manage the project schedule?

Revise the project schedule and inform the stakeholders regarding any delays

Revise the project estimates and meet with the project team to discuss delays

Review the management reserve to identify any costs associated with the delays

Review the contingency reserve to identify any delays to the project

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A new systems project requires feedback from the accounting manager at the beginning of solution discussions and before meeting with other functional managers. The project manager knows the accounting manager will not be available until a few days before the deadline for the solution document. What should the project manager do to avoid a delay in the project?

Ask the accounting manager to delegate a team member who can support the project.

Wait for the accounting manager to be available while identifying subsequent tasks that can be compressed,

Request that the sponsor direct the accounting manager's supervisor to provide a replacement resource,

Begin discussions with other functional managers and meet with the accounting manager later.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What should an agile lead do lo ensure their team is set up for success?

Pay attention to team dynamics and understand that coaching is done simultaneously at an individual and whole-team level

Schedule sprint meetings and coaching sessions to discuss project-related information

Plan quarterly informal meetings or team bonding sessions to encourage the team to work together

Document team tasks and challenges in order to understand when to step in and help a member of the team

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is leading a project with a predictive approach for a governmental body with strictly defined requirements. In the middle of the project, the sponsor requires a significant new feature to be included. This feature was not in the original plan, nor was it part of the planning process,What should the project manager do?

Descope low-priority features that were not explicitly requested and add this feature as a high priority.

Inform the senior manager that they will need a new project management plan for this feature,

Complete the most current feature and release the resources for the new feature.

Analyze the impact of this change and present the options to the senior manager.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During protect execution the project manager observes lower velocity and a high volume of tasks m the testing queue. The project is using a hybrid approach and there are only a few sprints remaining.What should the project manager do?

Work with the team to understand and solve the issues

Provide testing training to all the project team members

Increase the sprint duration so the testing can be completed

Add a new resource with testing skills to the team

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?