1.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Upon completion of a new electrical installation after successful verification and testing has taken place, what must be issued?

A. A minor works certificate

B. A new installation certificate

C. A periodic inspection certificate

D. An electrical installation certificate

Answer explanation

Amendment 2 (Brown Book) Reference: Page 238, section 644.1

2.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

An insulation test on a circuit with a nominal voltage of 600 Volts will require the test instrument to deliver a test voltage of?

1000 V

250 V

500 V

600 V

Answer explanation

Amendment 2 (Brown Book) Reference: Page 234, table 64

3.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Which one of these people signs a Minor Electrical Installation Works Certificate? Mark one answer

Designer

Inspector

Person ordering the works

Skilled competent persons

Answer explanation

Amendment 2 (Brown Book) Reference: Page 238, section 644.5

4.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

What method may be used to confirm the separation of a SELV circuit from other Circuits?

By asking the manufacturer

By calculation

By enquiry

By measurement

Answer explanation

Amendment 2 (Brown Book) Reference: Page 234, section 643.4.1

5.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Who shall make an initial verification of a new installation? Mark one answer

A. A skilled person

B. The architect

C. The designer

D. The person ordering the work

Answer explanation

Amendment 2 (Brown Book) Reference: Page 231, section 641.6

6.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

If all of the following tests are required in a new electrical installation, which of the listed tests must be performed first before the installation is energised? Mark one answer

Earth electrode resistance

Insulation resistance

Polarity

Protection by SELV

Answer explanation

Amendment 2 (Brown Book) Reference: Page 233, section 643.1

7.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

With regards to initial verification and testing, the verification process shall include comparison of the results with the relevant criteria to confirm that the requirements of the regulations?

Are no worse than the previous test results

Are the same as the previous test results

Have been met

Have been recorded in the schedule or works results

Answer explanation

Amendment 2 (Brown Book) Reference: Page 232, section 641.3

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?