Project Management Communication and RIsk Management Quiz

Quiz
•
Business
•
University
•
Medium
Irina Purcarea
Used 1+ times
FREE Resource
18 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During a business project, Mia noticed that the team was not communicating effectively about their tasks and deadlines. What is a consequence of poor project communication?
Misalignment between project deliverables and stakeholder expectations
Streamlined reporting and documentation processes
Increased agility in adapting to project changes
Enhanced cross-functional collaboration
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Ethan is managing a project and regularly sends out project status reports and newsletters to keep everyone informed. Which type of communication is he using?
Pull Communication
Interactive Communication
Push Communication
Formal Communication
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During a team project, Aiden frequently updates his team about their progress. What is a key component of effective communication?
Frequent updates
Vague messaging
Frequent and long meetings
Limited feedback
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In planning a group project for their class, what should Michael include in the communication plan?
Only Michael's preferences
Identifying key stakeholders
A list of all project tasks
A budget for communication tools
5.
MULTIPLE CHOICE QUESTION
30 sec • 5 pts
During a project to develop a new app, when should feedback be provided by the project manager, Ethan?
Only during formal meetings
At any time and as soon as possible
Only at the end of the project
Only when requested by team members
6.
MULTIPLE SELECT QUESTION
1 min • 1 pt
During a team project, Anika and her team decided to hold a meeting to discuss their progress. Which of the following are examples of interactive communication they might use?
A live video conference where team members can speak and ask questions
An email update sent to all team members
A face-to-face meeting to exchange ideas and provide feedback
A shared document that team members can read but not edit
7.
MULTIPLE CHOICE QUESTION
1 min • 5 pts
During a team project, Rohan noticed that some team members were not contributing effectively. He decided to hold a meeting to address the issues. What is a crucial skill in project communication that Rohan should practice during this meeting?
Giving feedback
Avoiding meetings
Delegating tasks
Active listening
Create a free account and access millions of resources
Similar Resources on Wayground
15 questions
Quiz on Special Topics on Financial Management

Quiz
•
University
20 questions
MARKETING MANAGEMENT

Quiz
•
University
20 questions
Events management quiz

Quiz
•
University
15 questions
Effective team working

Quiz
•
12th Grade - Professi...
15 questions
Health and Safety - Vocabulary

Quiz
•
University
15 questions
Project Management_Execution

Quiz
•
University
14 questions
9. Monitoring and Controlling Progress

Quiz
•
University
20 questions
Project Management Quiz

Quiz
•
University
Popular Resources on Wayground
10 questions
Video Games

Quiz
•
6th - 12th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
10 questions
UPDATED FOREST Kindness 9-22

Lesson
•
9th - 12th Grade
22 questions
Adding Integers

Quiz
•
6th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
20 questions
US Constitution Quiz

Quiz
•
11th Grade
10 questions
Exploring Digital Citizenship Essentials

Interactive video
•
6th - 10th Grade