1.
MULTIPLE CHOICE QUESTION
2 mins • 20 pts
Kumar, the project manager of the Antom project, is reviewing his project schedule network diagram, which is shown on the screen.
What is the free float of Activity AC?
Activity AC has a free float of 2 days
Activity AC has a free float of 6 days
Activity AC has a free float of zero days
Activity AC has a free float of 4 days
2.
MULTIPLE CHOICE QUESTION
2 mins • 20 pts
You are currently executing some activities in the Monitor and Control Project Work process. Which of the following may be part of these activities?
Providing forecasts to update current cost
Ensuring that the project stays aligned with the business needs
Determining whether the corrective actions are effective
All the above
3.
MULTIPLE CHOICE QUESTION
2 mins • 20 pts
You are taking over a project in your organization because of its schedule delay and you are requested to control this schedule. The first step you took was collecting information.
If the planned value was $132 K, which of the following will be your SPI?
0.9
1.1
1.0
1
4.
MULTIPLE CHOICE QUESTION
2 mins • 20 pts
After executing the Validate Scope process, which of the following describes the best way to deal with the resulted work performance information?
The information about the deliverables, which have been accepted and which have not been accepted and the reasons why are documented and added to the lessons learned register
The information about the deliverables, which have been accepted and which have not been accepted and the reasons why are documented and communicated to the stakeholders
The information about the deliverables that have been accepted is documented and communicated to the stakeholders
The information about the deliverables that have not been accepted and the reasons why are documented and communicated to the stakeholders
5.
MULTIPLE CHOICE QUESTION
2 mins • 20 pts
You are managing a project for the first time in your organization. You are executing the earned value analysis from time to time to review the project performance.
Today when executing the same analysis, you got a planned value of 450, actual cost of 480, and the CPI was 0.95. What is the status of your project work?
More project work was completed than planned
Less project work was completed than planned
Project work was completed as planned
None of the above
Similar Resources on Wayground
10 questions
Indicador Implementación del Modelo de Gestión Proyectos

Quiz
•
Professional Development
8 questions
CO-PO Mapping

Quiz
•
Professional Development
10 questions
Kuis nya Tukang Insinyur

Quiz
•
Professional Development
7 questions
Pre & Post Test FMS

Quiz
•
Professional Development
10 questions
Data Types

Quiz
•
Professional Development
10 questions
Numpy

Quiz
•
Professional Development
10 questions
Security Fundamentals and Windows OS Security

Quiz
•
Professional Development
10 questions
M4.3 Cat A - Servomechanisms - Inductive Transmitters

Quiz
•
Professional Development
Popular Resources on Wayground
55 questions
CHS Student Handbook 25-26

Quiz
•
9th Grade
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
10 questions
Chaffey

Quiz
•
9th - 12th Grade
15 questions
PRIDE

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
22 questions
6-8 Digital Citizenship Review

Quiz
•
6th - 8th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade