Quiz 5 Training Project Management [17/04/25]

Quiz 5 Training Project Management [17/04/25]

Professional Development

5 Qs

quiz-placeholder

Similar activities

Sensor quiz2

Sensor quiz2

Professional Development

10 Qs

Engineering April Quiz

Engineering April Quiz

Professional Development

10 Qs

EE 030 S2

EE 030 S2

Professional Development

10 Qs

Cyber Security for Remote Users

Cyber Security for Remote Users

Professional Development

10 Qs

Calculations in C-R & L-R Circuits Quiz

Calculations in C-R & L-R Circuits Quiz

Professional Development

10 Qs

Coimbatore master plan 2041

Coimbatore master plan 2041

Professional Development

10 Qs

Number Systems Quiz

Number Systems Quiz

Professional Development

8 Qs

Quiz 1 Training Project Management [15/04/25]

Quiz 1 Training Project Management [15/04/25]

Professional Development

5 Qs

Quiz 5 Training Project Management [17/04/25]

Quiz 5 Training Project Management [17/04/25]

Assessment

Quiz

Engineering

Professional Development

Practice Problem

Medium

Created by

Bella Fadli

Used 2+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

2 mins • 20 pts

Media Image

Kumar, the project manager of the Antom project, is reviewing his project schedule network diagram, which is shown on the screen.

What is the free float of Activity AC?

Activity AC has a free float of 2 days

Activity AC has a free float of 6 days

Activity AC has a free float of zero days

Activity AC has a free float of 4 days

2.

MULTIPLE CHOICE QUESTION

2 mins • 20 pts

You are currently executing some activities in the Monitor and Control Project Work process. Which of the following may be part of these activities?

Providing forecasts to update current cost

Ensuring that the project stays aligned with the business needs

Determining whether the corrective actions are effective

All the above

3.

MULTIPLE CHOICE QUESTION

2 mins • 20 pts

You are taking over a project in your organization because of its schedule delay and you are requested to control this schedule. The first step you took was collecting information.

If the planned value was $132 K, which of the following will be your SPI?

0.9

1.1

1.0

1

4.

MULTIPLE CHOICE QUESTION

2 mins • 20 pts

After executing the Validate Scope process, which of the following describes the best way to deal with the resulted work performance information?

The information about the deliverables, which have been accepted and which have not been accepted and the reasons why are documented and added to the lessons learned register

The information about the deliverables, which have been accepted and which have not been accepted and the reasons why are documented and communicated to the stakeholders

The information about the deliverables that have been accepted is documented and communicated to the stakeholders

The information about the deliverables that have not been accepted and the reasons why are documented and communicated to the stakeholders

5.

MULTIPLE CHOICE QUESTION

2 mins • 20 pts

You are managing a project for the first time in your organization. You are executing the earned value analysis from time to time to review the project performance.

Today when executing the same analysis, you got a planned value of 450, actual cost of 480, and the CPI was 0.95. What is the status of your project work?

More project work was completed than planned

Less project work was completed than planned

Project work was completed as planned

None of the above