SBEQ2523 Payment & Certificates

SBEQ2523 Payment & Certificates

University

15 Qs

quiz-placeholder

Similar activities

SIA 101-MODULE 13

SIA 101-MODULE 13

University

10 Qs

Famous Buildings and their Architects

Famous Buildings and their Architects

8th Grade - Professional Development

15 Qs

SITE VISIT QUIZ

SITE VISIT QUIZ

University

10 Qs

Random Construction Questions

Random Construction Questions

11th Grade - University

16 Qs

1. Arbitration and Methods of Dispute Resolution

1. Arbitration and Methods of Dispute Resolution

University

10 Qs

Introduction to CAD

Introduction to CAD

7th Grade - University

10 Qs

Roof Finishes

Roof Finishes

University

20 Qs

BUILDING UTILITIES PART 3_MECHANICAL

BUILDING UTILITIES PART 3_MECHANICAL

University

20 Qs

SBEQ2523 Payment & Certificates

SBEQ2523 Payment & Certificates

Assessment

Quiz

Architecture

University

Practice Problem

Easy

Created by

FARRAH A

Used 2+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary obligation of the employer in a construction contract?

Supervising the contractor's work

Making timely payment to the contractor

Certifying materials on site

Preparing the final account

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

According to Clause 30.1, what happens if a contractor fails to submit a payment application?

The architect must still issue a certificate

The contractor waives his entitlement to payment for that period

The QS can certify payment on his behalf

The employer becomes liable for breach of contract

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who is responsible for issuing the Interim Certificate?

Contractor

Quantity Surveyor

Architect

Employer

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Within how many days must the architect issue the Interim Certificate after receiving a valid payment application?

14 days

21 days

30 days

7 days

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the role of the Quantity Surveyor under Clause 30.1?

Sign the final account

Issue interim certificates

Value the contractor's application

Represent the contractor

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Under Clause 30.2, which of the following is NOT included in the amount due in an Interim Certificate?

Total value of work executed

Estimated future work

Value of stored materials

Less retention and previously certified sums

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is a condition for including materials in an Interim Certificate?

Materials must be adjacent to the site

Materials must be properly stored and secured

Materials must be intended for temporary works

Materials must be paid by subcontractors

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?