
CAPM domain 2, task 1,2
Authored by Aygun Aliyeva
Professional Development
Professional Development
Used 1+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
15 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a web development project, the client requests an additional feature midway that affects multiple existing work packages in the WBS. How should the project manager ensure that the WBS remains a reliable project planning tool?
Update the WBS to reflect new work packages and integrate changes with existing ones
Continue with the current WBS to avoid project scope alteration
Inform the client that changes are not possible after WBS development
Revise the project schedule to include the new feature without altering the WBS
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You have just been assigned to the new smartwatch project and are given the authority to choose your project lifecycle approach. Given what you know about the organization, which option would you select?
Adaptive because the project is very large, and everyone is working remotely
Predictive because the company promotes self-managed teams
Adaptive because the company has an inflexible chain of command
Predictive because the company is structured as a rigid hierarchy
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You have just completed the planning phase of the condominium renovation project, and you are following a waterfall approach. What are the activities and artifacts that your team will have just completed?
The contractor just completed the construction of the plumbing and electrical.
Detailed designs, schedules, and cost baselines were created.
All quality reports indicated deliverable inspections were satisfactory. The final inspection of the facility was made.
A business case was completed, and a verification that the firm has the available resources to meet the sponsor's timeframe was done.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In your software as a service (SAAS) project, the following activities have just occurred: the customer and project sponsor accepted the software, and customer support has just been engaged to help the customer install the product. Which phase do these activities represent?
Closing
Testing
Deployment
D.Design
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are managing a software development project budgeted at $525,000, according to the earned value analysis report you just generated. You see that your schedule dictated that the planned value of the work your team was scheduled to complete (PV) should be $310,000. However, the team has only completed $285,000 in value (EV). Additionally, your team has spent $350,000 (AC) so far. Which of the following is true about the status of your project?
You have a schedule variance of $25,000
You have a schedule variance of $65,000
You have a schedule variance of −$65,000
You have a schedule variance of −$25,000
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following best describes a work breakdown structure?
The WBS is a hierarchical decomposition of the total scope of work, beginning with themes and decomposed into epics and user stories.
The WBS is a hierarchical decomposition of the total scope of work decomposed down to control accounts.
The WBS is a hierarchical decomposition of the total scope of work to accomplish project ojectives.
The WBS is a hierarchical decomposition of the total scope of work to accomplish the product objectives.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following best describes a work package?
The work package is the lowest level of WBS decomposition for which cost and duration can be estimated and managed.
The work package is a level of WBS decomposition that represents scope but will be progressively elaborated on as time progresses.
The work package is a level of WBS decomposition where the project scope, budget, and cost are integrated to establish performance measurements.
The work package is the highest level of WBS decomposition for which schedule and cost can be realistically estimated and managed.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
15 questions
Comunicación Asertiva
Quiz
•
Professional Development
15 questions
BJT - BASICS
Quiz
•
Professional Development
18 questions
Collocation
Quiz
•
Professional Development
12 questions
Maslow's theory test
Quiz
•
Professional Development
20 questions
contract law 3-elements
Quiz
•
Professional Development
10 questions
Seminario DUA
Quiz
•
Professional Development
12 questions
Test de emprendimiento
Quiz
•
Professional Development
15 questions
Emerging Tech
Quiz
•
Professional Development
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
22 questions
fractions
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade
15 questions
Equivalent Fractions
Quiz
•
4th Grade
20 questions
Figurative Language Review
Quiz
•
6th Grade