CAPM domain 2, task 1,2

CAPM domain 2, task 1,2

Professional Development

15 Qs

quiz-placeholder

Similar activities

Project Procurement Management

Project Procurement Management

Professional Development

20 Qs

PM Framework Definitions

PM Framework Definitions

Professional Development

10 Qs

PMP Questions 6th Edition Quiz 3

PMP Questions 6th Edition Quiz 3

Professional Development

20 Qs

Project Integration Revision

Project Integration Revision

Professional Development

10 Qs

PMP Lesson 7

PMP Lesson 7

Professional Development

16 Qs

PMP RESOURCE MANAGEMENT Rev.2

PMP RESOURCE MANAGEMENT Rev.2

Professional Development

19 Qs

All-In-One Project+ PK0-005 Exam Guide - Chapter 05

All-In-One Project+ PK0-005 Exam Guide - Chapter 05

Professional Development

15 Qs

Módulo 6 (3,4 y 5)

Módulo 6 (3,4 y 5)

Professional Development

15 Qs

CAPM domain 2, task 1,2

CAPM domain 2, task 1,2

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Aygun Aliyeva

Used 1+ times

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a web development project, the client requests an additional feature midway that affects multiple existing work packages in the WBS. How should the project manager ensure that the WBS remains a reliable project planning tool?

Update the WBS to reflect new work packages and integrate changes with existing ones

Continue with the current WBS to avoid project scope alteration

Inform the client that changes are not possible after WBS development

Revise the project schedule to include the new feature without altering the WBS

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You have just been assigned to the new smartwatch project and are given the authority to choose your project lifecycle approach. Given what you know about the organization, which option would you select?

Adaptive because the project is very large, and everyone is working remotely

Predictive because the company promotes self-managed teams

Adaptive because the company has an inflexible chain of command

Predictive because the company is structured as a rigid hierarchy

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You have just completed the planning phase of the condominium renovation project, and you are following a waterfall approach. What are the activities and artifacts that your team will have just completed?

The contractor just completed the construction of the plumbing and electrical.

Detailed designs, schedules, and cost baselines were created.

All quality reports indicated deliverable inspections were satisfactory. The final inspection of the facility was made.

A business case was completed, and a verification that the firm has the available resources to meet the sponsor's timeframe was done.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In your software as a service (SAAS) project, the following activities have just occurred: the customer and project sponsor accepted the software, and customer support has just been engaged to help the customer install the product. Which phase do these activities represent?

Closing

Testing

Deployment

D.Design

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You are managing a software development project budgeted at $525,000, according to the earned value analysis report you just generated. You see that your schedule dictated that the planned value of the work your team was scheduled to complete (PV) should be $310,000. However, the team has only completed $285,000 in value (EV). Additionally, your team has spent $350,000 (AC) so far. Which of the following is true about the status of your project?

You have a schedule variance of $25,000

You have a schedule variance of $65,000

You have a schedule variance of −$65,000

You have a schedule variance of −$25,000

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following best describes a work breakdown structure?

The WBS is a hierarchical decomposition of the total scope of work, beginning with themes and decomposed into epics and user stories.

The WBS is a hierarchical decomposition of the total scope of work decomposed down to control accounts.

The WBS is a hierarchical decomposition of the total scope of work to accomplish project ojectives.

The WBS is a hierarchical decomposition of the total scope of work to accomplish the product objectives.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following best describes a work package?

The work package is the lowest level of WBS decomposition for which cost and duration can be estimated and managed.

The work package is a level of WBS decomposition that represents scope but will be progressively elaborated on as time progresses.

The work package is a level of WBS decomposition where the project scope, budget, and cost are integrated to establish performance measurements.

The work package is the highest level of WBS decomposition for which schedule and cost can be realistically estimated and managed.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?