1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which project management model is best suited for projects with clear and fixed requirements?

Agile Model

Spiral Model

Waterfall Model

V-Model

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a key limitation of the Agile methodology?

Difficult to involve the customer

Inflexibility to change

Testing is done only at the end

Less predictable timelines

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which model combines iterative development with risk analysis?

Agile

V-Model

Spiral Model

Waterfall

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a major strength of the V-Model?

Cost-effectiveness

Late-stage testing

High focus on quality

High flexibility

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the Delphi technique used for in software effort estimation?

Breaking down work into tasks

Anonymous group estimation to reduce bias

Measuring lines of code

Cost modeling based on time

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Function Point Analysis (FPA) is based on:

The size of source code

Number of developers

Functional components delivered to the user

Duration of each task

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which effort estimation model uses historical data from similar past projects?

Expert Judgment

COCOMO

Delphi

Analogy-Based Estimation

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?