1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Create a CP diagram. (You will turn it in)
Based on the image, what is the critical path?
(I pre-mapped the tasks and their predecessors for you.)
A, G, H, D, B
A, B, C, F
A, B, D, G, H
A, B, C, E, F
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Using a CP you created from this chart, what is the latest we can start project F without a delay in the project?
Day 5
Day 14
Day 16
Day 19
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Using a CP you created from this chart, what is the earliest a team can complete it?
Day 5
Day 14
Day 16
Day 19
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Revise your CP diagram. Once task A was completed, the team ran into a 2-week delay on materials for task E. If task E begins on day 18, what is our new early finish time for the entire project?
25 days
19 days
32 days
26 days
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the critical path in a project?
The path that uses the least money
The longest path of tasks that determines the project’s duration
C. The shortest path
with the least number of tasks
The tasks that are the easiest to complete
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
If a task on the critical path is delayed, what happens to the project?
Nothing changes
The project will finish earlier
The whole project will be delayed
Only that task will be skipped
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the float (or slack) time for tasks on the critical path?
A. One week
B. Zero
C. Unlimited
D. As much as the manager wants
1 week
zero
unlimited
as much as the team needs
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
10 questions
MANAGEMENT FUNCTIONS & ROLES
Quiz
•
11th Grade
10 questions
WHAT ARE YOU DOING?
Quiz
•
10th Grade
10 questions
Who Is An Entrepreneur Vocabulary Quiz
Quiz
•
8th - 9th Grade
10 questions
Entrepreneurship Unit 1
Quiz
•
11th - 12th Grade
11 questions
Production Possibility Frontier
Quiz
•
10th - 12th Grade
12 questions
Bonds and Funds Quiz
Quiz
•
12th Grade
10 questions
S1 Business Enterprise Hwk 1
Quiz
•
8th - 9th Grade
10 questions
5 x 5 Rule
Quiz
•
9th - 12th Grade
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
10 questions
Probability Practice
Quiz
•
4th Grade
15 questions
Probability on Number LIne
Quiz
•
4th Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
22 questions
fractions
Quiz
•
3rd Grade
6 questions
Appropriate Chromebook Usage
Lesson
•
7th Grade
10 questions
Greek Bases tele and phon
Quiz
•
6th - 8th Grade