24-25Critical Path Test Prep

24-25Critical Path Test Prep

9th - 12th Grade

7 Qs

quiz-placeholder

Similar activities

BMT13 Critical Path Analysis

BMT13 Critical Path Analysis

12th Grade

10 Qs

15 - Critical Path Analysis & Gantt Charts

15 - Critical Path Analysis & Gantt Charts

12th Grade

8 Qs

Internal Organizational Structure

Internal Organizational Structure

10th Grade

10 Qs

Vocabulary in International Business

Vocabulary in International Business

12th Grade

10 Qs

Time management

Time management

12th Grade

10 Qs

Executive Function

Executive Function

10th Grade

10 Qs

Project Scope Video & Questions

Project Scope Video & Questions

9th - 12th Grade

10 Qs

Office English Essentials: Unit 6 - Quiz 1

Office English Essentials: Unit 6 - Quiz 1

12th Grade

10 Qs

24-25Critical Path Test Prep

24-25Critical Path Test Prep

Assessment

Quiz

Business

9th - 12th Grade

Easy

Created by

Bobbie Jones

Used 2+ times

FREE Resource

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

Create a CP diagram. (You will turn it in)

Based on the image, what is the critical path?

(I pre-mapped the tasks and their predecessors for you.)

A, G, H, D, B

A, B, C, F

A, B, D, G, H

A, B, C, E, F

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

Using a CP you created from this chart, what is the latest we can start project F without a delay in the project?

Day 5

Day 14

Day 16

Day 19

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

Using a CP you created from this chart, what is the earliest a team can complete it?

Day 5

Day 14

Day 16

Day 19

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

Revise your CP diagram. Once task A was completed, the team ran into a 2-week delay on materials for task E. If task E begins on day 18, what is our new early finish time for the entire project?

25 days

19 days

32 days

26 days

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the critical path in a project?

The path that uses the least money

The longest path of tasks that determines the project’s duration

C. The shortest path

with the least number of tasks

The tasks that are the easiest to complete

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

If a task on the critical path is delayed, what happens to the project?

Nothing changes

The project will finish earlier

The whole project will be delayed

Only that task will be skipped

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the float (or slack) time for tasks on the critical path?
A. One week
B. Zero
C. Unlimited
D. As much as the manager wants

1 week

zero

unlimited

as much as the team needs