Monitor and Control Project Work - Assignment

Monitor and Control Project Work - Assignment

Professional Development

5 Qs

quiz-placeholder

Similar activities

Cost Management Terms - Assignment

Cost Management Terms - Assignment

Professional Development

5 Qs

Intelligent Delivery: Game KNB?!!

Intelligent Delivery: Game KNB?!!

Professional Development

10 Qs

Agile Concepts

Agile Concepts

Professional Development

10 Qs

SG20_Test_S3_Ch4_Integration

SG20_Test_S3_Ch4_Integration

Professional Development

10 Qs

Risk Response Strategies (Negative) - Assignment

Risk Response Strategies (Negative) - Assignment

Professional Development

7 Qs

Introduction to Project Management

Introduction to Project Management

Professional Development

10 Qs

Project Integration Revision

Project Integration Revision

Professional Development

10 Qs

Quick test about 12 principles in Agile

Quick test about 12 principles in Agile

Professional Development

9 Qs

Monitor and Control Project Work - Assignment

Monitor and Control Project Work - Assignment

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Afghanistan Center

FREE Resource

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Logar province, the project manager compares actual cost and schedule performance against the baselines to identify any variances that could affect the project's success. Which process is the project manager performing?

Monitor and Control Project Work

Perform Integrated Change Control

Manage Project Knowledge

Direct and Manage Project Work

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Nimroz province, the project team identifies that the actual project costs are 15% higher than planned and recommends a cost-saving action plan. What activity is happening?

Validating Deliverables

Identifying Variances and Recommending Corrective Actions

Capturing Tacit Knowledge

Finalizing Procurement Contracts

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Farah province, while reviewing project progress, the project manager collects and analyzes work performance data such as hours worked, milestones achieved, and costs incurred. What is this activity an example of?

Developing a Communications Management Plan

Gathering Work Performance Data

Managing Project Risks

Closing Project or Phase

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Cochabamba city in Bolivia, after a status review, the project team realizes that some deliverables are behind schedule and escalates the issue to the change control board. Which action aligns with Monitor and Control Project Work?

Updating the Business Case

Reviewing Performance and Recommending Preventive Actions

Developing the Procurement Plan

Validating Deliverables

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Sar-e-Pul province, during a project performance review, the project sponsor asks for a report showing comparisons of actual versus planned performance in scope, schedule, and cost. What report would typically be produced during this process?

Work Performance Reports

Risk Register

Lessons Learned Register

Project Charter