1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The road connecting district head quarters of a state

State Highway

National Highway

Major district road

Minor district road

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When wheels slide without revolving, the phenomenon is called

Skidding

Sliding

Slip

Spalling

3.

REORDER QUESTION

45 sec • 1 pt

The sequence of various engineering surveys which are carryout for the choice of a new highway project from beginning are

Location survey

Reconnaissance survey

Preliminary survey

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Recommended land width of major district roads in open areas in plain and rolling terrain in meters

15

20

25

45

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

If a vehicle is moving with a speed of 80 kmph, the absolute minimum sight distance required if t = 2.5 sec and f = 0.36 is

200 m

125 m

640 m

250 m

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

While calculating the sight distances, the drivers eye above road surface is assumed

90 cm

100 cm

110 cm

120 cm

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

_________________ is the distance required from the center line of a horizontal curve to an obstruction on inner side of the curve to provide adequate view at a horizontal curve

Sight distance

Length of curve

Set back

Radius of curve

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Microsoft

Continue with Microsoft

or continue with

Facebook

Facebook

Apple

Apple

Others

Others

Already have an account?