Search Header Logo

PMI PMP - Quality & Risk End of Lesson 3

Authored by Arun Sharma

Other

Professional Development

Used 28+ times

PMI PMP - Quality & Risk End of Lesson 3
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project has been closed and customer care needs to measure customer satisfaction with the deliverables.

What should be done next?

Negotiate additional contract with customer for similar service.

Schedule meeting with stakeholders and customer to discuss lessons learned.

Evaluate project deliverables and review customer feedback documents.

Audit project success by reviewing closing documentation for each project phase.

Answer explanation

C. Evaluate project deliverables and review customer feedback documents

Evaluate- Closure meetings are used to confirm deliverables have been accepted, validate if acceptance criteria have been met, formalize contract completion, evaluate stakeholders satisfaction, gather lessons learned, transfer project knowledge and information, and celebrate success. Customer satisfaction can be derived by referring customer feedback documents

Negotiate- Not initiated by the customer. No need to negotiate additional contract with customer

Schedule- Previously performed at project closure. As part of Project closure meeting, lessons learned can be covered

Audit- No relevance to the question, part of gate review process

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The client agreed to the standards that would be used to assess final deliverables prior to hand-off, but is now asking for improvements because the deliverables do not meet the standards. Which document should the project manager consult to resolve this issue?

Scope management plan

Quality management plan

Requirements documentation

  1. D.Project charter

Answer explanation

B. Quality management plan

The quality management plan defines the standards for the project deliverables and how compliance with the standards can be demonstrated. The project charter will not have this level of detail. Likewise, the scope and requirements should not change or list specific responses to the quality acceptance criteria of the project deliverables.

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

After sponsor approval of a project, the project manager invites the sponsor, selected team members, and other stakeholders to a meeting. The major purpose of the meeting is to define how formal acceptance of the completed project deliverables will be obtained.

What document will be developed as the final output of this meeting?

Change log.

Stakeholder register.

Scope management plan.

Requirements management plan.

Answer explanation

C. Scope management plan

The scope management plan is a component of the project management plan that describes how the scope will be defined, developed, monitored, controlled, and validated.

Change log is used to document changes that occur during a project.

Stakeholder register contains information about identified stakeholders that includes identification information, assessment information and stakeholder classification.

Requirements management plan is a component of the project management plan that describes how project and product requirements will be analyzed, documented, and managed.

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A manufacturing company receives customer complaints that a product is defective. A project sponsor has said that these complaints might be outliers.

What should the project manager use to investigate the cause and quantity of defects in this product?

Flowcharts

Affinity diagram

Control chart

Histogram

Answer explanation

D. Histogram

Histogram is correct because it can show the number of defects per deliverable, a ranking of the cause of defects, the number of times each process is noncompliant, or other representations of project or product defects.

Flowchart is not correct because it show a series of steps that lead to a defect.

Affinity diagram is not correct because it can organize potential causes of defects into groups showing areas that should be focused on the most.

Control chart is not correct because it is used to determine whether or not a process is stable or has predictable performance

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A major project deliverable is completed. What should the project manager and team do to confirm that specifications have been met?

Check the organizational process assets.

  1. Validate the quality audit reports.

Verify the scope.

Perform quality control.

Answer explanation

D. Perform quality control

Quality control is used to analyze and evaluate the project deliverables against the requirements.

The other answer choices are incorrect. Quality audits are typically used to address problems or improvements, not to validate deliverable specifications. Organizational process assets are specific to the organization and not to the project, or project deliverables. Verifying the scope is not helpful, as the deliverable has already been completed.

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project manager is working with stakeholders to identify the steps that must be completed as part of a task. The project manager needs to be able to verify that team members have completed all the steps required when performing a frequently performed task.

What should the project manager use?

Flowchart

Checklist

Histogram

Facilitation

Answer explanation

B. Checklist

The project manager should use a checklist as it is generally used in validating process steps have been implemented.

The other answer choices are incorrect. Flowcharts can only be used to outline process steps not verify that they have been conducted; histograms reflect frequency distribution and will not verify team members have completed the tasks; and facilitation is the ability to effectively guide a group event to a successful decision, solution, or conclusion.

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A customer is concerned that the current project deliverable will not fulfill stated project requirements. What could be done to alleviate customer concerns?

Schedule a meeting to remind the customer of requirements previously communicated to the team.

Document the customer's concern as a risk in the risk register and plan accordingly.

Manage the concern at the review of each deliverable with the customer.

Ask a product owner to review the acceptance criteria previously discussed with the customer.

Answer explanation

D. Ask a product owner to review the acceptance criteria previously discussed with the customer

To align the customer expectations with the upcoming deliveries the product owner should work with the customer to describe functional behavior as acceptance criteria (definition of Done).

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?