1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Before any tasks begin in Nimroz province, the project sponsor and manager draft a document that formally authorizes the project and names the project manager. Which process is being performed?

Develop Project Charter

Develop Project Management Plan

Initiate Work Package Authorization

Authorization phase involving governance modeling, stakeholder pre-alignment, and escalation mapping

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Laghman province, the project team brings together scope, cost, schedule, communication, and other subsidiary plans into a single guiding document. What process does this describe?

Develop Project Management Plan

Direct and Manage Project Work

Monitor and Control Project Work

Consolidation of performance domains through integrated planning, phased baseline formation, and configuration tracking

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

While building a clinic in Kapisa province, the team begins executing the project plan, managing resources, and delivering outputs. The manager resolves issues as they arise and ensures deliverables are being created. Which process is in action?

Direct and Manage Project Work

Control Scope

Perform Integrated Change Control

Real-time implementation of planned activities using progressive delivery tracking and team task execution

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Kabul, the team reviews lessons learned from a recently completed IT project to help improve planning for their current education project. They document and share both successes and failures with the team. Which integration process is being used?

Manage Project Knowledge

Monitor and Control Project Work

Close Project or Phase

Organizational learning cycle involving reflective knowledge mapping and outcome-based documentation

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

While reviewing progress in Parwan province, the PM compares actual results to the project plan and takes corrective action to get the project back on track. What process is taking place?

Monitor and Control Project Work

Direct and Manage Project Work

Perform Integrated Change Control

Phase-tracking process using milestone variance checks, real-time adjustments, and performance forecasting

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Jalalabad, a stakeholder submits a change request to add more features to a public information system. The project manager and change control board review and decide whether to approve the request. What process is being followed?

Perform Integrated Change Control

Control Scope

Monitor Risks

Centralized evaluation of scope modification through formal review, risk analysis, and impact-based decision criteria

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

As a hospital expansion project wraps up in Balkh province, the manager ensures that all deliverables are accepted, final reports are completed, and lessons learned are archived. Which process is being executed?

Close Project or Phase

Control Scope

Monitor and Control Project Work

Exit process combining administrative closure, knowledge capture, and formal stakeholder acknowledgment

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Microsoft

Continue with Microsoft

or continue with

Facebook

Facebook

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?

Discover more resources for Professional Development