Integration Process - Assignment

Integration Process - Assignment

Professional Development

7 Qs

quiz-placeholder

Similar activities

Schedule Management Processes - Assignment

Schedule Management Processes - Assignment

Professional Development

6 Qs

Contributing to the delivery of a project

Contributing to the delivery of a project

Professional Development

12 Qs

Stakeholder Management - Assignment

Stakeholder Management - Assignment

Professional Development

7 Qs

Procurement 10 soal (Chapter 12)

Procurement 10 soal (Chapter 12)

Professional Development

10 Qs

Project Management Module

Project Management Module

Professional Development

10 Qs

Practice Exam 2 Part 2

Practice Exam 2 Part 2

Professional Development

10 Qs

Practice Exam 2 Part 1

Practice Exam 2 Part 1

Professional Development

11 Qs

Validate and Control Scope - Assignment

Validate and Control Scope - Assignment

Professional Development

6 Qs

Integration Process - Assignment

Integration Process - Assignment

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Afghanistan Center

FREE Resource

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Before any tasks begin in Nimroz province, the project sponsor and manager draft a document that formally authorizes the project and names the project manager. Which process is being performed?

Develop Project Charter

Develop Project Management Plan

Initiate Work Package Authorization

Authorization phase involving governance modeling, stakeholder pre-alignment, and escalation mapping

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Laghman province, the project team brings together scope, cost, schedule, communication, and other subsidiary plans into a single guiding document. What process does this describe?

Develop Project Management Plan

Direct and Manage Project Work

Monitor and Control Project Work

Consolidation of performance domains through integrated planning, phased baseline formation, and configuration tracking

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

While building a clinic in Kapisa province, the team begins executing the project plan, managing resources, and delivering outputs. The manager resolves issues as they arise and ensures deliverables are being created. Which process is in action?

Direct and Manage Project Work

Control Scope

Perform Integrated Change Control

Real-time implementation of planned activities using progressive delivery tracking and team task execution

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Kabul, the team reviews lessons learned from a recently completed IT project to help improve planning for their current education project. They document and share both successes and failures with the team. Which integration process is being used?

Manage Project Knowledge

Monitor and Control Project Work

Close Project or Phase

Organizational learning cycle involving reflective knowledge mapping and outcome-based documentation

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

While reviewing progress in Parwan province, the PM compares actual results to the project plan and takes corrective action to get the project back on track. What process is taking place?

Monitor and Control Project Work

Direct and Manage Project Work

Perform Integrated Change Control

Phase-tracking process using milestone variance checks, real-time adjustments, and performance forecasting

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Jalalabad, a stakeholder submits a change request to add more features to a public information system. The project manager and change control board review and decide whether to approve the request. What process is being followed?

Perform Integrated Change Control

Control Scope

Monitor Risks

Centralized evaluation of scope modification through formal review, risk analysis, and impact-based decision criteria

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

As a hospital expansion project wraps up in Balkh province, the manager ensures that all deliverables are accepted, final reports are completed, and lessons learned are archived. Which process is being executed?

Close Project or Phase

Control Scope

Monitor and Control Project Work

Exit process combining administrative closure, knowledge capture, and formal stakeholder acknowledgment