1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Before any tasks begin in Nimroz province, the project sponsor and manager draft a document that formally authorizes the project and names the project manager. Which process is being performed?
Develop Project Charter
Develop Project Management Plan
Initiate Work Package Authorization
Authorization phase involving governance modeling, stakeholder pre-alignment, and escalation mapping
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Laghman province, the project team brings together scope, cost, schedule, communication, and other subsidiary plans into a single guiding document. What process does this describe?
Develop Project Management Plan
Direct and Manage Project Work
Monitor and Control Project Work
Consolidation of performance domains through integrated planning, phased baseline formation, and configuration tracking
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
While building a clinic in Kapisa province, the team begins executing the project plan, managing resources, and delivering outputs. The manager resolves issues as they arise and ensures deliverables are being created. Which process is in action?
Direct and Manage Project Work
Control Scope
Perform Integrated Change Control
Real-time implementation of planned activities using progressive delivery tracking and team task execution
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Kabul, the team reviews lessons learned from a recently completed IT project to help improve planning for their current education project. They document and share both successes and failures with the team. Which integration process is being used?
Manage Project Knowledge
Monitor and Control Project Work
Close Project or Phase
Organizational learning cycle involving reflective knowledge mapping and outcome-based documentation
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
While reviewing progress in Parwan province, the PM compares actual results to the project plan and takes corrective action to get the project back on track. What process is taking place?
Monitor and Control Project Work
Direct and Manage Project Work
Perform Integrated Change Control
Phase-tracking process using milestone variance checks, real-time adjustments, and performance forecasting
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Jalalabad, a stakeholder submits a change request to add more features to a public information system. The project manager and change control board review and decide whether to approve the request. What process is being followed?
Perform Integrated Change Control
Control Scope
Monitor Risks
Centralized evaluation of scope modification through formal review, risk analysis, and impact-based decision criteria
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
As a hospital expansion project wraps up in Balkh province, the manager ensures that all deliverables are accepted, final reports are completed, and lessons learned are archived. Which process is being executed?
Close Project or Phase
Control Scope
Monitor and Control Project Work
Exit process combining administrative closure, knowledge capture, and formal stakeholder acknowledgment
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Microsoft
or continue with
%20(1).png)
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?