
PMP Full Mock - CS 2
Authored by Arun Sharma
Other
Professional Development

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
175 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Your organization has a standing ethics review committee, and you are a member of this committee. A complaint has been filed against a project manager for allegedly violating a number of company policies. If the allegations are proved, she would be terminated for cause. During the investigation, her boss has been uncooperative. He asked the committee investigators to not to contact his employee directly and has tried to slow down the process of investigation. What should you do?
Answer explanation
Escalate the issue to the appropriate management. PMI requires project managers to report known instances of wrong doing to the appropriate management. However, the actions that are taken by the organization investigating the complaint must be in line with that organization's own policies. Only the management of the organization can interpret or apply those rules. [PMI Code of Ethics and Professional Conduct] (Domain: Business Environment, Task 1)
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
When reviewing quarterly expenses for your project with the finance department, it becomes clear there is a discrepancy between the projected, budgeted, and actual costs incurred for equipment procured from a specific vendor. This cost variance puts the project over budget by 2 percent, inclusive of reserves. After reviewing and comparing the quotes with the invoices, it is discovered that the quotes were issued in Canadian dollars while the invoices were issued in US dollars. Which of the following is the best option?
Answer explanation
Notify project stakeholders immediately and accept responsibility for the error. PMI's code of ethics requires project managers to provide accurate and timely project information—including bad news—and to take full responsibility for all errors and omissions. Whenever there is an impact to cost, scope, or schedule, the project manager must notify the project stakeholders; once they have been notified, analysis of options to deal with the impact can be undertaken. [PMI Code of Ethics and Professional Conduct] (Domain: Business Environment, Task 1)
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Team Building Activities should take place throughout the project lifecycle but will have greater benefit when conducted:
Answer explanation
Team Building Activities should take place throughout the project life cycle, but have greater benefit when conducted early in the project life cycle. [PMBOK® Guide 7th edition, Page 166] (Domain: People, Task 6)
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The Budget at Completion (BAC) for a project is $50,000. The Actual Costs (AC) to date are $10,000. The Earned Value (EV) is $7,000. At this stage, the project management team did a manual bottom-up summation of costs and forecast an Estimate to Complete (ETC) of $50,000. What is the Estimate at Completion (EAC) for the project?
Answer explanation
When a bottom-up manual forecasting has been done for the ETC, the calculation for EAC is EAC = AC + bottom-up ETC. Hence, EAC = 10,000 + 50,000 = $60,000. Note that the BAC is no longer viable at this stage. [PMBOK® Guide 7th edition, Page 100-105] (Domain: Process, Task 5)
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You have recently taken over a project that has been struggling to keep key project stakeholders engaged since inception. The project requires developing an ERP system for your organization and the project currently is in the design phase. A number of stakeholders are complaining that the current design doesn’t match their stated requirements. Which of the following tools will help you trace the design to the requirements?
Answer explanation
The requirements traceability matrix provides a structure to trace requirements to product design. [PMBOK® Guide 7th edition, Page 189] (Domain: Process, Task 8)
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Your project team has recently completed the 3rd iteration on the project. So far 45 story points have been successfully delivered to the customer. For this project, the iteration size is fixed at three weeks. The team (six team members) is dedicated to working five days per week. Looking at the backlog, you have 150 story points remaining to be delivered. What is the project’s cycle time?
Answer explanation
Cycle time = number of days per delivered story. Since the team has successfully delivered 45 stories in 3 iterations, the velocity is 15 stories per iteration. Each iteration is 3 weeks; the team delivers on average five stories per week or one story per day (team works five days per week). [Agile Practice Guide, 1st edition, Page 61] (Domain: Process, Task 6)
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Many environments with emerging requirements find that there is often a gap between the real business requirements and the business requirements that were originally stated. How do Agile method identify the right business requirements?
Answer explanation
Agile methods purposefully build and review prototypes and release versions in order to refine business requirements. [Agile Practice Guide, 1st edition, Page 91] (Domain: Process, Task 8)
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?