In Parwan province, the project team conducts training for all workers on the new quality standards before starting construction. What type of action is this?
Prevention Vs Correction - Assignment

Quiz
•
Professional Development
•
Professional Development
•
Hard
Afghanistan Center
FREE Resource
7 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Preventive Action
Corrective Action
Defect Repair
Proactive quality alignment effort through resource education, error blocking, and execution forecasting
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
After testing the software in Badakhshan province, the team identifies and fixes bugs before delivery to the customer. What quality-related activity is this?
Defect Repair
Preventive Action
Root Cause Prevention
Functional restoration using issue mapping, gap resolution, and post-approval component realignment
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Following a review in Ghor province, the team updates the work process to prevent the recurrence of recent quality issues. What is this an example of?
Preventive Action
Corrective Action
Change Request
System-wide quality safeguard involving pattern disruption and process redesign
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
After an inspection in Logar province, the manager notices the output does not match the plan. The team takes immediate steps to realign progress with the baseline. What is this response called?
Corrective Action
Preventive Action
Defect Repair
Alignment recalibration involving workstream analysis and downstream flow acceleration
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Balkh province, the project manager focuses on building quality into the process to avoid issues later, rather than fixing them afterward. Which quality philosophy does this reflect?
Prevention over Inspection
Defect Repair
Scope Validation
Cost-risk balance through post-delivery tolerance reduction and stakeholder-reported issue mapping
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During construction in Helmand province, a concrete wall is discovered to be out of alignment and must be rebuilt to meet design specs. What type of quality activity is this?
Defect Repair
Preventive Action
Quality Assurance
Output realignment through physical rework and defect reconfiguration protocol
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Kandahar province, the quality team creates a checklist to be used before every major delivery to reduce the chance of errors. What is this an example of?
Preventive Action
Corrective Action
Control Rework
Error-blocking mechanism using standardized inspection triggers and pre-delivery safeguard steps
Similar Resources on Quizizz
8 questions
ISO 9001 Awareness

Quiz
•
Professional Development
7 questions
Prevention VS Correction - Assignment

Quiz
•
Professional Development
7 questions
Final Quiz - Assignement

Quiz
•
Professional Development
10 questions
Quality Problem-Solving Strategies

Quiz
•
Professional Development
8 questions
Quiz Lesson 5 - Topic E (Manage Project Changes)

Quiz
•
Professional Development
12 questions
8D Problem Solving

Quiz
•
Professional Development
12 questions
Quality Assurance Ch 1 Part 2

Quiz
•
Professional Development
10 questions
QUALITY CONTROL

Quiz
•
Professional Development
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade