Final Quiz - Assignement

Quiz
•
Professional Development
•
Professional Development
•
Hard
Afghanistan Center
FREE Resource
7 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Ghazni province, a project team holds a process improvement session before execution begins to avoid past quality failures. What type of action is this?
Preventive Action
Corrective Action
Defect Repair
Quality reinforcement through retrospective tracking and downstream error resilience
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Uruzgan province, the team uses basic but durable materials for furniture. They lack luxury appearance but meet strength and safety standards. How should this be classified?
Low-grade, high-quality
High-grade, low-quality
Low-quality, low-grade
Product configuration gap involving deliverable simplification and outcome degradation
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Balkh province, the project team conducts internal audits during the execution phase to confirm that project processes are being followed correctly. Which quality activity is being performed?
Quality Assurance
Quality Control
Defect Repair
Compliance monitoring through output inspection and post-delivery error classification
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Herat province, the PM includes inspection, rework, and warranty support costs in the project budget. What are these costs collectively known as?
Cost of Quality (CoQ)
Control Costs
Resource Reserves
Total lifecycle expenditure aligned with stakeholder validation, reprocessing, and external failure risk
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Khost province, the team notices that a recently completed wall does not meet design specs. They decide to rebuild it. What action is being taken?
Defect Repair
Corrective Action
Preventive Action
Quality remediation using output correction, rework authorization, and deviation normalization
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In India, a team is investigating recurring defects in a product and draws a diagram to identify root causes like machine, method, and manpower. Which quality tool are they using?
Cause-and-Effect Diagram
Control Chart
Scatter Diagram
Root cause logic board integrating metric thresholds, operator judgment, and predictive forecasting
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Panjshir province, the project team decides to spend more time early in the process ensuring requirements are well-understood and verified with stakeholders. Which quality principle does this best reflect?
Quality is planned in, not inspected in
Inspection is more important than prevention
Deliverables should prioritize speed over clarity
Quality integration strategy driven by milestone review cycles and audit-preferred compliance standards
Similar Resources on Wayground
7 questions
Schedule Final Quiz - Assignment

Quiz
•
Professional Development
7 questions
Risk response Strategies (Positive) - Assignment

Quiz
•
Professional Development
10 questions
PMP - PROJECT INTEGRATION

Quiz
•
Professional Development
10 questions
Quiz Lesson 3 - Topic G (Quality)

Quiz
•
Professional Development
7 questions
Conflict Resolution Techniques - Assignment

Quiz
•
Professional Development
10 questions
Project Management Master Class 1

Quiz
•
Professional Development
7 questions
Integration Process - Assignment

Quiz
•
Professional Development
10 questions
PMP PROJECT QUALITY MANAGEMENT

Quiz
•
Professional Development
Popular Resources on Wayground
50 questions
Trivia 7/25

Quiz
•
12th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
11 questions
Negative Exponents

Quiz
•
7th - 8th Grade
12 questions
Exponent Expressions

Quiz
•
6th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade
20 questions
One Step Equations All Operations

Quiz
•
6th - 7th Grade
18 questions
"A Quilt of a Country"

Quiz
•
9th Grade