Project Cost Management Quiz

Project Cost Management Quiz

University

30 Qs

quiz-placeholder

Similar activities

chương 2 hhđc

chương 2 hhđc

University

26 Qs

DSL 204 Brakes MIDTERM

DSL 204 Brakes MIDTERM

University

25 Qs

Midterms in PED226 [Test 1}

Midterms in PED226 [Test 1}

University

25 Qs

Nhóm 3

Nhóm 3

University

26 Qs

C05 CUSTOMER LIAISON 1/3

C05 CUSTOMER LIAISON 1/3

University

25 Qs

Series Practice Quiz

Series Practice Quiz

University

25 Qs

UT.4: GESTIÓN DE LA DOCUMENTACIÓN BÁSICA

UT.4: GESTIÓN DE LA DOCUMENTACIÓN BÁSICA

University

25 Qs

宴會管理期中考(選擇題)

宴會管理期中考(選擇題)

University

35 Qs

Project Cost Management Quiz

Project Cost Management Quiz

Assessment

Quiz

Professional Development

University

Hard

Created by

Harie Arema

Used 2+ times

FREE Resource

30 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Earned Value is defined as?

A. The amount of earnings the project has accrued

B. The amount of earnings the team members have taken home

C. Value of completed work expressed as a proportion of the current budget ​

D. The amount of earnings that will be a potential outcome of the project

2.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

2. Which of the following is an input to “Plan Quality Management”?

A. Enterprise Environmental Factors

B. Quality Management Plan

C. Cost-Benefit Analysis

D. Quality Checklists

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

 

3. Cash flow is the expected cash outgoings distributed over time, whereas cost flow is the projection of incurred cost distributed over time.

A. True

B. False

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

4. Which of the following is a PBS (Package Breakdown Structure):

A. Client’s preferred cost reporting structure ​

B. Breakdown of work into physical geographical areas

C. Breakdown of work which reflects the execution strategy ​

D. Breakdown of work which aligns with the asset strategy of the client ​

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

5. Project change notices are merely notices to the client and don’t require approval in order to be added to the baseline documents.

A. True

B. False

6.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

6. Project Control is the responsibility of the Project Controls team.

A. True

B. False

7.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

7. Which one is NOT a project controls discipline at Hatch:

A. Planning and Scheduling

B. Cost Management

C. Estimating

D. Deliverable Control

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?

Discover more resources for Professional Development