SPM Pre-test
Authored by Miranty Scantya
Information Technology (IT)
University
Used 2+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A _______ is a series of actions directed toward a particular result
goal
process
plan
project
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
____________ processes include coordinating people and other resources to carry out project plans and create the products, services, or results of the project or phase.
Initiating
Planning
Executing
Closing
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which process group normally requires the most resources and time?
Initiating
Planning
Executing
Monitoring and Controlling
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following outputs is often completed before initiating a project?
Stakeholder register
Business case
Project charter
Kick-off meeting
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A work breakdown structure, project schedule, and cost estimates are outputs of the ____________ process.
initiating
planning
executing
monitoring and controlling
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Initiating involves developing a project charter, which is part of the project ____________ management knowledge area.
integration
scope
communications
risk
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
____________ involves measuring progress toward project objectives and taking corrective actions.
Initiating
Planning
Executing
Monitoring and controlling
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?