Search Header Logo

PMP - Arun Kumar - Daily Practice Questions

Authored by Deepak Kumar Meena

Other

Professional Development

Used 1+ times

PMP - Arun Kumar - Daily Practice Questions
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

71 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project involving seven partners is falling behind schedule. The steering committee decides that all conflict resolution attempts must be speed up and requests that the project manager remove the requirement for all parties to make concessions. What should the project manager do?

Eliminate the withdraw/avoid technique.

Eliminate the smooth/accommodate technique.

Eliminate the force/direct technique.

Eliminate the compromise/reconcile technique.

Answer explanation

The compromise/reconcile technique is a conflict resolution technique in which both parties give up something in order to reach an agreement. If one party is not required to make any concessions, then it is not possible for both parties to compromise.

The other answer choices are incorrect as they are not eliminated by the steering committee's decision. Withdraw/avoid: This technique involves withdrawing from the conflict or avoiding it altogether. The project manager can still allow the parties to use this technique, as long as they do not delay the project. Smooth/accommodate: This technique involves giving in to the other party's demands to avoid conflict. The project manager can still allow the parties to use this technique, as long as they do not delay the project. Force/direct: This technique involves using one's power or authority to get the other party to agree to one's demands. The project manager can still allow the parties to use this technique, as long as they do not delay the project.

This question and rationale were developed in reference to:

PMBOK Guide Seventh Edition (2022) PMI/PMI/ [4.2.7.1 CONFLICT MODEL]

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project is in the execution phase, and product testing is almost complete. A team member proposes that the testing can be fast-tracked by removing some of the tests. The team member believes this will help to finish the job earlier and give the project more float.

What should the project manager do?

Request more information from the team member.

Reject the team member's proposal.

Discuss this proposal with the project team.

Ask the quality manager to consider the proposal.

Answer explanation

Solution: B. Reject the team member's proposal

Removing certain tests is a risky move, and can't be done just to fast-track the project. The Project Manager should have considered all tests while assigning time for the testing phase. If the project is progressing as per the assigned time, no review of tests is needed, and the proposal should be rejected.

This question and rationale were developed in reference to:

Fundamentals of Technology Project Management, 2nd Ed (2015) Colleen Garton, Erika McCulloch/Mc Press/11/400

| PMBOK Guide Sixth Edition (2018) PMI/PMI/8/293

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A manufacturing company receives customer complaints that a product is defective. A project sponsor has said that these complaints might be outliers.

What should the project manager use to investigate the cause and quantity of defects in this product?

Flowcharts

Affinity diagram

Control chart

Histogram

Answer explanation

Solution: D. Histogram

Histogram is correct because it can show the number of defects per deliverable, a ranking of the cause of defects, the number of times each process is noncompliant, or other representations of project or product defects.

Flowchart is not correct because it show a series of steps that lead to a defect.

Affinity diagram is not correct because it can organize potential causes of defects into groups showing areas that should be focused on the most.

Control chart is not correct because it is used to determine whether or not a process is stable or has predictable performance

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project to develop a new product is nearing its closing phase after 6 months of contributions from the project team and vendor. The project manager has confirmed that the project satisfied the strategic goal it was meant to achieve and received formal documented acceptance from the client and sponsor.

What should the project manager do next?

Review all contracts with the project team and suppliers.

Disband the project team and return resources to their functional location.

Ensure customer care teams have the training to perform their role.

Document lessons learned for future reference.

Answer explanation

Solution: A. Review all contracts with the project team and suppliers.

When the project manager has confirmed that the project satisfied the strategic goal it was meant to achieve and received formal documented acceptance from the client and sponsor, they should review all contracts with the project team and suppliers. They should make sure that all parties have satisfied their contractual obligations—that the suppliers have delivered all of the products or services required of them and that the organization has made all pertinent payments.

The other answer choices are incorrect. Ensuring customer care teams have the training to perform their role should occur during the project, well before closure. Documenting lessons learned can come after contracts have been reviewed. Disbanding the project team and returning resources to their functional location should be the very last step.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A firm is currently facing a cost overrun and needs liquidity to overcome the financial crisis. A critical project is underway and is expected to bring a reasonable monetary return for the firm, yet, the project is over budget. Senior management needs to assess the project's alignment with organizational objectives and requests that the project manager provide a report on the matter.

What should the project manager do to prepare a report for management?

Examine and evaluate documents to gain insights and extract meaningful information.

Compare actual results to planned ones by analyzing the differences between actual performance and budgeted values.

Identify and analyze patterns, tendencies, or changes in data over a specific period of time.

Assess the economic feasibility of the project, by comparing the costs with the benefits expected by senior management.

Answer explanation

Solution: B. Compare actual results to planned ones by analyzing the differences between actual performance and budgeted values.

The project manager should compare the actual results of the project to the planned ones by analyzing the differences between actual performance and budgeted values. Comparing actual results to planned ones allows the project manager to assess the project's financial performance and understand where it deviates from the budgeted values. Once the project manager has identified the specific areas where the project is over budget and the root causes of these overruns, they can develop recommendations for addressing these problems and getting the project back on track.

The other options are incorrect because they are not the most directly relevant actions to take when cost overruns and organizational alignment are the primary concerns.

Examining and evaluating documents lacks specificity in addressing the financial crisis and the need to assess the project's alignment with organizational objectives.

Identifying and analyzing patterns may help identify broader trends in the project's performance, but it is not the most directly relevant action.

Assessing the economic feasibility of the project focuses more on the overall economic viability of the project rather than the immediate concerns of cost overruns and organizational alignment.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager works in a matrix organization. Following a reorganization, several key project resources are reassigned to another project. The project no longer has the resources needed to successfully deliver the project.

What should the project manager do?

Refuse to release the newly reassigned resources.

Review the communications management plan.

Review resource allocation and utilization plans.

Review resource needs with the functional manager.

Answer explanation

Solution: D. Review resource needs with the functional manager.

In a matrix environment, the project resources are typically shared between multiple projects. The project manager should review the project's resource needs with the functional manager because the resources report to their functional managers. The project manager should explain the impact of reassigning the resources and work with the functional manager to minimize the impact of the resource reassignment.

The other answer choices are incorrect.

Refusing to release the reassigned resources is not feasible and is beyond the project manager's authority. Reviewing the communications management plan is not relevant to the situation. Reviewing resource allocation and utilization plans does not address the current resource shortage.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is beginning a new financial software project in a very competitive environment. The regulations for compliance are clear, but the requirements are not clear. The customer stresses that they need results as soon as possible.

Which implementation approach should the project manager choose for this project?

Repeating and refining project phases in multiple iterations.

Progressing through a linear sequence of stages.

Embracing change and focusing on delivering value.

Focusing on delivering the project in multiple increments.

Answer explanation

Solution: D. Focusing on delivering the project in multiple increments.

Focusing on delivering the project in multiple increments is correct because it delivers value to the customer before the final project release. Incremental delivery ensures that the customer gets usable and valuable functionality early in the project. This aligns with the customer's desire for quick results and allows for their feedback to be incorporated. Since the requirements are unclear and the environment is competitive, getting feedback from the customer early will reduce rework, promote stakeholder involvement, and provide an early return on investment.

The other options are incorrect because they are not as well-suited for this project.

Repeating and refining project phases in multiple iterations is incorrect because, although this approach allows for early deployment of some functionalities of the project, clarifying requirements with the customer before developing any aspect of the project is more cost effective.

Progressing through a linear sequence of stages is incorrect because it assumes that all requirements can be defined upfront, which is not the case when requirements are unclear. It does not allow for early deployment and the customer will not have an opportunity to clarify requirements until after major development work is done.

Embracing change and focusing on delivering value is a valuable mindset but lacks a specific implementation approach tailored to the challenges of this project.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?