BPPA_Day 8 on BoQ

BPPA_Day 8 on BoQ

Professional Development

9 Qs

quiz-placeholder

Similar activities

Interviewing Skills

Interviewing Skills

Professional Development

13 Qs

FOUNDATION COURSE

FOUNDATION COURSE

Professional Development

11 Qs

Assessment

Assessment

Professional Development

10 Qs

MA - Accounting for Labour

MA - Accounting for Labour

Professional Development

13 Qs

Post Test SeBBar Ferizyan #006

Post Test SeBBar Ferizyan #006

Professional Development

10 Qs

Black History Month

Black History Month

Professional Development

10 Qs

DICEST - Talent Khoj - 8-April

DICEST - Talent Khoj - 8-April

Professional Development

10 Qs

CTET 29/05/2020

CTET 29/05/2020

Professional Development

10 Qs

BPPA_Day 8 on BoQ

BPPA_Day 8 on BoQ

Assessment

Quiz

Professional Development

Professional Development

Practice Problem

Medium

Created by

Shah Islam

Used 1+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

9 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 15 pts

Which of the following shall be considered in evaluation process?

Amount related to Price Adjustment provision

Dayworks

Physical contingencies in a contract

Amount payable to the Nominated Sub-contractor

2.

MULTIPLE CHOICE QUESTION

30 sec • 10 pts

Pre-Qualification does not waive Post-Qualification. The statement is-

False

True

3.

MULTIPLE CHOICE QUESTION

30 sec • 10 pts

To make Pre-Qualification process an effective one, how many pre-qualified applicants will be required?

Minimum 3

Minimum 5

Maximum 7

No limit

4.

MULTIPLE CHOICE QUESTION

30 sec • 10 pts

In International tenders, no national tenderer can participate. The statement is -

True

False

5.

MULTIPLE CHOICE QUESTION

45 sec • 15 pts

In international procurement, when any part of a contract is to be executed wihin Bangladesh, that part shall be quoted in.....

Bangladeshi Taka

Any foreign currency allowed in the contract.

Any currency as per tenderer's will

All of the above

6.

MULTIPLE CHOICE QUESTION

30 sec • 10 pts

Joint Venture is not generally allowed in which category of procurement as per the PPR 2008?

Works

Consultancy Service

Physical Service

Goods

7.

MULTIPLE CHOICE QUESTION

30 sec • 10 pts

All partners of a JV shall be jointly and severally liable for execution of the contract. The statement is -

FALSE

TRUE

8.

MULTIPLE CHOICE QUESTION

45 sec • 10 pts

Negotiations can be done in OTMs where...

Scope of works need to reduced

In international tender, LRT's price is quoted in foreign currencies

In both cases

In no case

9.

MULTIPLE CHOICE QUESTION

30 sec • 10 pts

An apparently non-responsive tender can be made responsive seeking clarifications from the tenderer. The statement is -

False

True