1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is starting a new project, and the project team is located in different countries. The team was going to use a specific tool to hold virtual meetings. However, that tool is not available in one team member's country. How should the project manager deal with this situation?
Contact the project sponsor to have the team member removed from the project
Ask the team member to move to another location where the tool is available
Investigate alternative tools for virtual meetings that are available to all team members
Start the project and use email to communicate with the team member until the tool is available
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Halfway through a project, the project sponsor is replaced by another peer who was not previously engaged in the project. The new project sponsor has rejected most of the project artifacts, and the team did not get the latest increment approved on the current iteration. Stakeholders are not feeling confident about the project outcome. What should the project manager have done to prevent this situation?
Performed a stakeholder analysis when the sponsor joined the project
Held a governance meeting to review the project increment
Escalated the issue to ensure the increment would be approved
Conducted a product iteration review with the new project sponsor
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A regulatory branch of an environmental government agency has recently placed a ban on the manufacturing of a specified thickness of plastic packaging products. This ban will take effect in 12 months. The project manager for a startup firm working in alternative packaging has been monitoring the progress of this law for a while and, as part of the risk management, has identified new products that can support a growing customer base. What should the project manager do next?
Begin a marketing campaign to sell alternative packaging after the 12-month period ends
Organize a meeting with all stakeholders and review the stakeholder engagement plan
Continue production processes and plan to discuss changes at the next annual target review meeting
Inform management of the new law as an opportunity to expand market share and share the proposed products
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is part of a balanced matrix project organization. The project manager will receive all work performance updates directly from the new sourcing department head who has no time to spare to give the project manager the information. What should the project manager do?
Discuss the situation with the company project sponsor for advice
Request information directly from the sourcing department team members
Work out a resolution in consultation with the sourcing department head
Present the situation to the manager of the sourcing department head
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager has just been hired by a company without a project management governance structure. During the kick-off meeting, a key stakeholder emphasizes the importance of the project meeting the company's strategy, investment, and compliance requirements. What should the project manager do?
Put into place a project governance model in line with the requirements
Replicate the organizational governance to the project governance
Create an organizational project management governance
Ask the organization to create a project portfolio governance
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A third-party supplier demands payment for the services provided for a project. The agreement was that payment would be made after the organization receives payment from the client. The third-party supplier lacks the capital to meet their payroll and has informed the project manager that if they do not receive payment quickly, they will withdraw team members from the project. What should the project manager do?
Explain the third-party supplier situation to the client and request payment.
Inform the client that the project must be delayed until payment is received.
Reassign resources from other projects to pay the third-party supplier.
Process a bank loan to pay the payroll of the third-party supplier.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is developing the stakeholder register and is having trouble understanding the motivation of some of the stakeholders. What should the project manager do to get this information?
Identify each stakeholder's motivations from the business case.
Request stakeholders articulate their motivations at the kick-off meeting.
Email project objectives to all stakeholders and ask for endorsement.
Organize a one-on-one conversation with each stakeholder.
Create a free account and access millions of resources
Similar Resources on Wayground
53 questions
mod 8

Quiz
•
Professional Development
51 questions
Quiz on SSH, NFS, and SMB

Quiz
•
Professional Development
51 questions
Kiến thức CNTT cơ bản P1

Quiz
•
Professional Development
48 questions
Project Management Quiz

Quiz
•
Professional Development
51 questions
Network Module Mid-Term Quiz 04

Quiz
•
Professional Development
45 questions
KSS QUIZ

Quiz
•
Professional Development
50 questions
Python_Mock

Quiz
•
Professional Development
45 questions
CCST - Networking

Quiz
•
Professional Development
Popular Resources on Wayground
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
11 questions
Hallway & Bathroom Expectations

Quiz
•
6th - 8th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
19 questions
Handbook Overview

Lesson
•
9th - 12th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade