Project Management Quiz

Project Management Quiz

Professional Development

46 Qs

quiz-placeholder

Similar activities

CySA+Sy Test 02

CySA+Sy Test 02

Professional Development

42 Qs

Linux - Up to Disk Partition

Linux - Up to Disk Partition

Professional Development

50 Qs

Python Final Assessment

Python Final Assessment

Professional Development

51 Qs

MQBC

MQBC

Professional Development

50 Qs

Final Coaching Set 1

Final Coaching Set 1

Professional Development

47 Qs

Project Management Quiz

Project Management Quiz

Assessment

Quiz

Information Technology (IT)

Professional Development

Hard

Created by

Minh Vũ

FREE Resource

46 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

After signing an agreement with a vendor, the project manager notices that the vendor is continuously asking for changes on the procurement statement of work (SOW). These changes would improve the project outcome. What should the project manager do next?

Consult the list of selected vendors for the bid and evaluate a possible change of vendor.

Revise the procurement control process to avoid undesired changes that might affect the schedule.

Assess the situation as an opportunity for improvement and perform a risk analysis.

Conduct an audit on the procurement process and inform the vendor about the audit's observations.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is performing earned value management (EVM) for a cross-country pipeline project. The project manager has determined the ratio of earned value (EV) to actual cost (AC) for the project and has found the calculated result to be 0.9024. What does this value mean for the project?

The project is earning less value than was planned

The project has started exceeding the planned cost

The project has earned more value than planned

The project is close to exceeding the planned cost

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A customer complains that the user stories released so far contain too much jargon and do not reflect the expectations of the product. What should the project manager do next?

Rewrite the stories to include the technical vision of the product

Ask the senior developer to rewrite all the stories

Engage with the customer and rewrite all the stories

Request approval from the company director to conduct training for the team

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An unforeseen event has shut down public works projects for 4 weeks. Activities on the critical path will fall behind based on the project schedule. What should the project manager do?

Add 4 additional weeks to the schedule and request additional resources.

Ask the sponsor to obtain a special work permit to continue work.

Crash the resource management plan to keep the schedule on track.

Review the project management plan to see the impact of the possible delay.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a regular project progress meeting, the CEO informed the project manager that a major stakeholder has been unaware of recent developments on the project. The project manager is sure that the stakeholder was duly identified and classified in the stakeholder register. Which project document should the project manager review in order to determine the reason for this issue?

Requirements traceability matrix

Issue log

Stakeholder register

Stakeholder engagement assessment matrix

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A healthcare organization hired a new compliance specialist to ensure that the healthcare compliance needs are met. The feedback about the new compliance specialist from the team was average. What should the project manager do to help the new compliance specialist improve?

Coordinate a one-to-one meeting with the specialist to assess the situation

Escalate this situation to the manager of the area for a possible solution

Provide time for the specialist to adjust to the pace of the project

Contact the human resources (HR) manager about the team's feedback

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A company has selected a cross-functional team to develop an innovative digital product to drive the digital transformation project for the business. What should the project manager do to ensure business value is delivered early?

Create robust incentives to the team members to encourage speedy delivery

Create a detailed project plan and escalate delays to the functional managers

Break down the deliverables into sprints and deliver value incrementally

Fast track the project and monitor tasks closely to ensure timely delivery

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?