IB CS Review 1 - 25/26

IB CS Review 1 - 25/26

9th - 12th Grade

20 Qs

quiz-placeholder

Similar activities

Computer Quiz for Grade 11 (SDLC, Waterfall & Agile)

Computer Quiz for Grade 11 (SDLC, Waterfall & Agile)

11th Grade

23 Qs

City & Guilds Award in Business Processes

City & Guilds Award in Business Processes

12th Grade

20 Qs

Software Testing Methodologies

Software Testing Methodologies

12th Grade

25 Qs

Software Development Life Cycle (practice)

Software Development Life Cycle (practice)

10th - 12th Grade

20 Qs

Waterfall Model Quiz

Waterfall Model Quiz

12th Grade

18 Qs

SEAC3 LO4 K-8 Testing and Documentation

SEAC3 LO4 K-8 Testing and Documentation

9th Grade

17 Qs

SYSTEM LIFE CYCLE REVISION

SYSTEM LIFE CYCLE REVISION

10th Grade

20 Qs

G10 REVISION IGCSE CH 7 Documentation & Evaluation

G10 REVISION IGCSE CH 7 Documentation & Evaluation

10th Grade

20 Qs

IB CS Review 1 - 25/26

IB CS Review 1 - 25/26

Assessment

Quiz

Computers

9th - 12th Grade

Easy

Created by

Benny William

Used 1+ times

FREE Resource

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the main goal of system design?
To develop user interfaces
To define requirements
To write code
To train staff

Answer explanation

System design focuses on defining system structure and requirements.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which method is used to collect data about how a system is currently used?
Questionnaires
User interface design
Prototyping
Testing

Answer explanation

Questionnaires help gather user opinions and habits.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which installation method runs the new system alongside the old one?
Direct changeover
Pilot
Parallel
Phased

Answer explanation

Parallel runs both systems together to ensure a smooth transition.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a disadvantage of the direct changeover method?
Requires more hardware
Takes longer
High risk if failure occurs
Costly

Answer explanation

Direct changeover is risky because the old system is immediately replaced.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which type of testing is done by the end users?
Alpha testing
Unit testing
Integration testing
Beta testing

Answer explanation

Beta testing is conducted by users to give feedback before full release.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT a feasibility study factor?
Technical
Operational
Economic
Statistical

Answer explanation

Statistical is not a standard feasibility criterion.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which stakeholders are MOST likely to use a system daily?
Developers
End users
Project managers
Testers

Answer explanation

End users are regular users of the system.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?