1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You notice that some of your project team members are not attending your meetings and that there has been an increase in requests for transfer from your project. These are examples of:
Risk triggers
Residual risks
Primary risks
Risk events
Answer explanation
Risk triggers are indicators that suggest potential risks may occur. The lack of meeting attendance and transfer requests signal underlying issues, making them risk triggers for your project.
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Each project management knowledge area is subdivided into __________
Categories
Best practices
Processes
Methods
Answer explanation
Each project management knowledge area is subdivided into processes, which are specific steps or activities that guide project execution. This structure helps in organizing and managing projects effectively.
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
All of the following statements about the project life cycle are true except:
The control needs of the organization will determine how many phases will be included in the project life cycle
Cost and staffing are at the highest levels during the start of the project
Project phases are typically completed sequentially but can be overlapped to accelerate completion of a project
Risk is at the highest levels of uncertainty at the start of the project
Answer explanation
The statement about cost and staffing being highest at the start is incorrect. Typically, costs and staffing peak during the execution phase, not at the start of the project.
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You have discovered a problem with one of the technical processes, which is needed to perform some of the work of your project. You decide to utilize a fishbone diagram for root cause analysis to determine the reason for the problem. Which of the following are you using?
Process analysis
Control quality
Perform quality assurance
Inspection
Answer explanation
Using a fishbone diagram for root cause analysis is part of control quality, as it helps identify issues affecting project processes. This method ensures that quality standards are met by addressing the root causes of problems.
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which of the following is not a good way to deal with a complex project?
Analyze and model
Diversity and balance
Avoidance
Teamwork
Answer explanation
Avoidance is not a good way to deal with a complex project, as it ignores challenges. In contrast, analyzing, diversity, and teamwork are effective strategies for managing complexity.
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
All of the following are examples of Enterprise Environmental Factors except:
Organizational culture
Existing facilities and infrastructure
Performance measurement criteria
Political climate
Answer explanation
Performance measurement criteria are not considered Enterprise Environmental Factors, as they are more related to project management processes rather than external influences like culture, infrastructure, or political climate.
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You have been selected as the project manager for a major infrastructure upgrade at your company headquarters. This means that:
The project plan has been progressively elaborated
Project selection processes have been initiated
The scope of the project has been verified
A project charter has been approved and signed by management
Answer explanation
As the project manager, the approval and signing of the project charter by management indicates that the project has been officially authorized to proceed, making it the correct choice.
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
25 questions
MA - Presenting Information
Quiz
•
Professional Development
25 questions
R2-VirtuQuest2024
Quiz
•
Professional Development
25 questions
21 Days Practice Project | Round 5 | Quiz 4
Quiz
•
KG - Professional Dev...
25 questions
Shopping
Quiz
•
Professional Development
25 questions
Finish the Worship Song Lyric
Quiz
•
7th Grade - Professio...
25 questions
ARXIU
Quiz
•
Professional Development
25 questions
Conexión Bíblica 2024 Aventureros - Primera Ronda
Quiz
•
Professional Development
25 questions
UNIT 206
Quiz
•
Professional Development
Popular Resources on Wayground
10 questions
Honoring the Significance of Veterans Day
Interactive video
•
6th - 10th Grade
9 questions
FOREST Community of Caring
Lesson
•
1st - 5th Grade
10 questions
Exploring Veterans Day: Facts and Celebrations for Kids
Interactive video
•
6th - 10th Grade
19 questions
Veterans Day
Quiz
•
5th Grade
14 questions
General Technology Use Quiz
Quiz
•
8th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
15 questions
Circuits, Light Energy, and Forces
Quiz
•
5th Grade
19 questions
Thanksgiving Trivia
Quiz
•
6th Grade