1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You notice that some of your project team members are not attending your meetings and that there has been an increase in requests for transfer from your project. These are examples of:
Risk triggers
Residual risks
Primary risks
Risk events
Answer explanation
Risk triggers are indicators that suggest potential risks may occur. The lack of meeting attendance and transfer requests signal underlying issues, making them risk triggers for your project.
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Each project management knowledge area is subdivided into __________
Categories
Best practices
Processes
Methods
Answer explanation
Each project management knowledge area is subdivided into processes, which are specific steps or activities that guide project execution. This structure helps in organizing and managing projects effectively.
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
All of the following statements about the project life cycle are true except:
The control needs of the organization will determine how many phases will be included in the project life cycle
Cost and staffing are at the highest levels during the start of the project
Project phases are typically completed sequentially but can be overlapped to accelerate completion of a project
Risk is at the highest levels of uncertainty at the start of the project
Answer explanation
The statement about cost and staffing being highest at the start is incorrect. Typically, costs and staffing peak during the execution phase, not at the start of the project.
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You have discovered a problem with one of the technical processes, which is needed to perform some of the work of your project. You decide to utilize a fishbone diagram for root cause analysis to determine the reason for the problem. Which of the following are you using?
Process analysis
Control quality
Perform quality assurance
Inspection
Answer explanation
Using a fishbone diagram for root cause analysis is part of control quality, as it helps identify issues affecting project processes. This method ensures that quality standards are met by addressing the root causes of problems.
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which of the following is not a good way to deal with a complex project?
Analyze and model
Diversity and balance
Avoidance
Teamwork
Answer explanation
Avoidance is not a good way to deal with a complex project, as it ignores challenges. In contrast, analyzing, diversity, and teamwork are effective strategies for managing complexity.
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
All of the following are examples of Enterprise Environmental Factors except:
Organizational culture
Existing facilities and infrastructure
Performance measurement criteria
Political climate
Answer explanation
Performance measurement criteria are not considered Enterprise Environmental Factors, as they are more related to project management processes rather than external influences like culture, infrastructure, or political climate.
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You have been selected as the project manager for a major infrastructure upgrade at your company headquarters. This means that:
The project plan has been progressively elaborated
Project selection processes have been initiated
The scope of the project has been verified
A project charter has been approved and signed by management
Answer explanation
As the project manager, the approval and signing of the project charter by management indicates that the project has been officially authorized to proceed, making it the correct choice.
Create a free account and access millions of resources
Similar Resources on Wayground
30 questions
bspk

Quiz
•
Professional Development
25 questions
Cybersecurity Quiz

Quiz
•
Professional Development
30 questions
Risk Management

Quiz
•
Professional Development
30 questions
R1-VirtuQuest2024

Quiz
•
Professional Development
25 questions
WEW - Health and Safety

Quiz
•
Professional Development
26 questions
Food Safety Level 1

Quiz
•
Professional Development
30 questions
Robby's Management Final Exam: Nearpod

Quiz
•
Professional Development
25 questions
PUNLA Pre-Test 2024

Quiz
•
Professional Development
Popular Resources on Wayground
12 questions
Unit Zero lesson 2 cafeteria

Lesson
•
9th - 12th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
11 questions
All about me

Quiz
•
Professional Development
20 questions
Lab Safety and Equipment

Quiz
•
8th Grade
13 questions
25-26 Behavior Expectations Matrix

Quiz
•
9th - 12th Grade
10 questions
Exploring Digital Citizenship Essentials

Interactive video
•
6th - 10th Grade
Discover more resources for Other
11 questions
All about me

Quiz
•
Professional Development
10 questions
How to Email your Teacher

Quiz
•
Professional Development
5 questions
Setting goals for the year

Quiz
•
Professional Development
14 questions
Disney Trivia

Quiz
•
Professional Development
14 questions
2019 Logos

Quiz
•
Professional Development
7 questions
How to Email your Teacher

Quiz
•
Professional Development
11 questions
NFL Football logos

Quiz
•
KG - Professional Dev...
20 questions
Employability Skills

Quiz
•
Professional Development