2391-52 Exam Practice 3 (IET)

2391-52 Exam Practice 3 (IET)

Vocational training

60 Qs

quiz-placeholder

Similar activities

Prévention du Basculement: Les Ancrages

Prévention du Basculement: Les Ancrages

KG - University

65 Qs

Key Content Areas - C1 Heat

Key Content Areas - C1 Heat

11th Grade

60 Qs

Revision 2

Revision 2

KG - University

60 Qs

Level One- PPE

Level One- PPE

KG - University

61 Qs

Objective

Objective

11th Grade

57 Qs

A1 Health and Safety in Construction

A1 Health and Safety in Construction

11th Grade - University

58 Qs

Unit 101 Short Answer AI Test 2 SE HW

Unit 101 Short Answer AI Test 2 SE HW

1st Grade - University

60 Qs

UJIAN KOMPETENSI TEKNIK BANGUNAN DAN LANDASAN ANGKATAN 15 A/B

UJIAN KOMPETENSI TEKNIK BANGUNAN DAN LANDASAN ANGKATAN 15 A/B

KG - University

57 Qs

2391-52 Exam Practice 3 (IET)

2391-52 Exam Practice 3 (IET)

Assessment

Quiz

Construction

Vocational training

Practice Problem

Hard

Created by

Paul Ward

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

60 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

1. What is the purpose of an initial verification?

To confirm the installation is defective or has not deteriorated over time.

To confirm the installation complies with the design or construction parts of BS 7671.

To confirm that the client is satisfied with all the work carried out.

To confirm that contractual elements have been undertaken to ISO 9001.

Answer explanation

Correct answer: b "To confirm the installation complies with the design or construction parts of BS 7671."

Guidance Note 3 (21) states that the purpose of an initial verification is to confirm, by way of inspection and testing, that the installation complies with the design and construction aspects of BS 7671, in so far as is reasonably practical.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

2. Why is periodic inspection and testing undertaken?

To provide an engineering view that an installation can continue to be used safely.

To provide proof that an alteration to an installation complies with current regulations.

To provide an engineering view that the installation was constructed correctly.

To provide proof that all additions to the installation comply with current regulations.

Answer explanation

Correct answer: a "To provide an engineering view that an installation can continue to be used safely."

Guidance Note 3 (3.1) states that the purpose of periodic inspection and testing is to provide an engineering view on whether or not the installation is in a satisfactory condition where it can continue to be used safely. All other options reference new work which involves initial verification.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

3. What situation would require the issue of an Electrical Installation Condition Report?

The addition of a light to an existing circuit.

The installation of a new distribution board.

Changing a building use from a house to a hotel.

Changing a radial circuit into a ring-final circuit.

Answer explanation

Correct answer: c "Changing a building use from a house to a hotel."

Where the use of a building changes, the local authority, as well as insurance companies, would require a report to determine the suitability of the installation for the new use.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

4. What is the most suitable document to be issued by an inspector following the addition of an outdoor socket-outlet supplied from an existing ring-final circuit?

Electrical Installation Certificate.

Building Controls Certification to Part P.

Electrical Installation Condition Report.

Minor Electrical Installation Works Certificate.

Answer explanation

Correct answer: d "Minor Electrical Installation Works Certificate."

Where the addition to an existing circuit does not extend to a new circuit, a Minor Electrical Installation Works Certificate would be the simplest document which can be issued by the inspector to certify the new work.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

5. What decision does an inspector need to make when undertaking periodic inspection, which is not required during initial verification?

The amount of sampling undertaken.

The type of certification to be used.

The suitability of the test instruments.

The suitability of test results obtained.

Answer explanation

Correct answer. a "The amount of sampling undertaken."

During periodic inspection and testing, the inspector would need to decide on the suitable amount of sampling required. Sampling is not undertaken for initial verification. Certification is not suitable for a periodic inspection and test instrument and result suitability applies in both cases.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

6. What non-statutory document contains the maximum values of earth fault loop impedance at normal test temperature?

Scenario: Refurbishment work has been undertaken in a small industrial unit. Two new socket-outlet radial circuits were installed and several luminaires replaced on an existing lighting circuit. There are no previous records or charts for the electrical installation so the client requires inspection and testing to the existing circuits. The unit is currently vacant so the inspector has no restrictions on circuit or installation isolation. The supply and installation form a 230 V, single-phase TN-C-S system.

BS 7671.

IET GN3.

HSE GS38.

EAWR.

Answer explanation

Correct answer: b "IET GN3."

Whilst BS 7671 does contain maximum values of earth fault loop impedance, they are values given for circuit normal operating temperatures. When testing is undertaken, these values need adjusting so Guidance Note 3 (Appendix A) has values which are already compensated for, so a direct comparison can be made.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

7. What must be carried out due to the lack of records and charts for the existing circuits?

Scenario: Refurbishment work has been undertaken in a small industrial unit. Two new socket-outlet radial circuits were installed and several luminaires replaced on an existing lighting circuit. There are no previous records or charts for the electrical installation so the client requires inspection and testing to the existing circuits. The unit is currently vacant so the inspector has no restrictions on circuit or installation isolation. The supply and installation form a 230 V, single-phase TN-C-S system.

Inspection would include cables concealed in walls.

A small sample of circuits would be tested first.

Inspection would include dismantling all equipment.

Exploratory work is done to determine circuit control.

Answer explanation

Correct answer: d "Exploratory work is done to determine circuit control."

Before any inspection or testing is carried out, the inspector must have the information relating to the control of each circuit and equipment. The inspector would need to carry out a full survey to do this.

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?