1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The project manager decides to move forward without allowing changes to the existing process. Which of the following techniques is the project manager using?

Forcing

Avoiding

Compromising

Smoothing

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The quarterly financial report displays losses from a project even though the project was completed successfully several weeks ago. Which of the following actions should the project manager perform next?

Remove access.

Complete the project sign-off.

Release the resources.

Outline the lessons learned.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project sponsor has asked for a log listing all the bugs identified within a specific project. Which of the following tools should the project manager provide to the sponsor?

Change log

Issue log

Risk register

Defect log

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following best describes the difference between the current state and the desired future state in project management?

A. The current state is a high-level view of the project scope, and the desired state is what is happening right now.

B. The current state is where the business is now, and the desired state is where the project is going

The current state is a high-level view of the project scope, and the desired future state is the

specific outcome the business wants.

The current state defines the specific outcome the business wants, and the desired state

documents what is happening now that prevents it.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager needs to update the project sponsor and senior stakeholders about the progress of a project. Which of the following tools will the project manager MOST likely use?

Dashboard

Gantt chart

Work breakdown structure

Requirements Traceability Matrix

6.

MULTIPLE SELECT QUESTION

30 sec • 1 pt

Which of the following activities are important parts of the closing phase? (Select two).

Locking risks

Completing the work breakdown structure

Releasing resources

Updating stakeholder register

Closing contracts

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A stakeholder raises a concern with a project manager because of the number of emails that have been received before a coding release. Which of the following actions should the project manager take next?

A. Inform the CCB to stop communication.

B. Establish a RACI matrix.

C. Escalate the communication issues.

D. Revise the communication plan.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?