
CHAP 13
Authored by Dang Anh
Life Project
University

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
68 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
1) The first step in the control cycle is:
Setting a goal.
Measuring progress.
Comparing actual with planned performance.
Taking action.
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
2) Project goal setting includes setting a baseline plan, which is predicated on:
The progress measurement.
An accurate work breakdown structure.
The type of gap analysis the project team plans to use.
The budget and schedule limitations.
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
3) Measurement mechanisms should include a clear definition of:
The project baseline.
The reporting relationships among members of the project team.
What to measure.
Trigger points.
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
4) A measurement process that determines the project goals and then the degree to which the actual performance lives up to these goals is:
A metric system.
Goal-performance linkage.
Five degrees of separation.
Gap analysis.
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
5) If significant deviations from the project plan are detected, corrective action is taken and then:
The monitoring and control cycle begins anew.
Project goals are adjusted to reflect current reality.
The project stakeholders are informed of the budget or time difficulties.
The critical chain is reviewed for task dependency.
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
12) The classic project S-curve is a plot of:
Labor hours versus money expended.
Money expended versus elapsed time.
Elapsed time versus labor hours.
Number of personnel versus days behind schedule.
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
13) Use the S-curve to choose the BEST statement about the project it describes. The horizontal axis is in weeks.
The total project costs in week 10 are less than budgeted.
The total project costs in week 10 exceed the budgeted cost.
The project cost more from weeks 25 through 30 than it did in weeks 10 through 15.
The total amount spent on the project at the end of the 20th week is approximately $30,000.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?