Critical Path Analysis Quiz
Authored by paul dunstan
Construction
Vocational training
Used 3+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
20 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a network diagram for critical path analysis, a node with an earliest start time of 10 and a latest finish time of 10 indicates which of the following?
The activity has a total float of 10 days
The node lies on the critical path with zero float
The activity must be delayed by 10 days
The node has a free float of 10 days
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following correctly defines "total float" in critical path analysis?
The amount of time an activity can be delayed without delaying the project end date
The amount of time an activity takes from its earliest start to its latest finish
The total duration of all activities along the critical path combined
The difference between the earliest start time and the latest start time of a project
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project has activities A, B, and C. Activity A takes 4 days, B takes 6 days, and C takes 3 days. If B and C both depend on A, what is the earliest finish time of the entire project?
The project finishes earliest at day 10 after A and B are completed
The project finishes earliest at day 13 after A, B, and C are all completed
The project finishes earliest at day 7 after A and C are completed
The project finishes earliest at day 9 after B and C run simultaneously
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a critical path network, the "earliest start time" (EST) of an activity is calculated by which of the following methods?
Subtracting the activity duration from the latest finish time of the preceding activity
Taking the maximum of the earliest finish times of all immediately preceding activities
Taking the minimum of the earliest finish times of all immediately preceding activities
Adding the total float to the latest start time of the preceding activity
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following statements about the critical path in a project network is correct?
The critical path is always the route with the fewest number of activities in the network
The critical path is the longest path through the network and determines project duration
The critical path is the shortest path through the network and determines project duration
The critical path is the route with the highest total float across all its activities
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In critical path analysis, "free float" is best described as which of the following?
The time by which an activity can be delayed without affecting the latest start of any successor
The time by which an activity can be delayed without affecting the earliest start of any successor
The total time available between the start and end of the entire project network
The difference between the latest finish time and the earliest finish time of the project
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project network has the following paths and durations: Path 1 = 20 days, Path 2 = 25 days, Path 3 = 22 days. Which path is the critical path and what is the project duration?
Path 1 is the critical path and the project duration is 20 days in total
Path 3 is the critical path and the project duration is 22 days in total
Path 2 is the critical path and the project duration is 25 days in total
All paths are critical and the project duration is 67 days in total
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?