1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The power of the State to acquire private property for public use without the owner’s consent is known as:
Police Power
Taxation
Eminent Domain
Escheat
Answer explanation
The power of the State to acquire private property for public use without the owner's consent is called Eminent Domain. This legal principle allows governments to take private land for projects that benefit the public.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which constitutional provision guarantees that private property shall not be taken without just compensation?
Article II, Section 4
Article III, Section 1
Article III, Section 9
Article XII, Section 18
Answer explanation
Article III, Section 9 of the Constitution explicitly states that private property cannot be taken for public use without just compensation, making it the correct provision for this question.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Republic Act No. 10752 primarily facilitates the acquisition of:
Government supplies
Public plazas
Right-of-Way for infrastructure projects
Indigenous lands only
Answer explanation
Republic Act No. 10752 is designed to streamline the process of acquiring Right-of-Way for infrastructure projects, ensuring that necessary land is available for development and public use.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which law did RA 10752 repeal?
RA 7160
RA 6957
RA 8974
CA 141
Answer explanation
RA 10752, known as the 'Right-of-Way Act', specifically repealed RA 8974, which was the previous law governing the right-of-way for national government infrastructure projects.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The cut-off date for informal settlers affected by a ROW project is:
Issuance of Notice to Proceed
Approval of the RAP
Start of census and tagging
Payment of just compensation
Answer explanation
The cut-off date for informal settlers in a ROW project is the 'Start of census and tagging', as this marks the point when affected individuals are officially identified for compensation and assistance.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which mode of acquisition is prioritized under RA 10752 before negotiated sale?
Expropriation
Donation
Lease
Exchange
Answer explanation
Under RA 10752, donation is prioritized as a mode of acquisition before considering negotiated sale. This emphasizes the preference for voluntary transfer of property over other methods.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
If the property owner rejects the negotiated sale offer within 30 days, the Implementing Office shall:
Revise the offer
Suspend the project
Initiate expropriation
Refer to LGU mediation
Answer explanation
If the property owner rejects the offer within 30 days, the Implementing Office must initiate expropriation to proceed with the project, as this is the next legal step when negotiations fail.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?