Microsoft Project 2021 From Beginners to Advanced - Deadlines and Constraints

Microsoft Project 2021 From Beginners to Advanced - Deadlines and Constraints

Assessment

Interactive Video

Information Technology (IT), Architecture

University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial explains the concept of task constraints in project scheduling, highlighting the default constraint of starting tasks as soon as possible. It explores various constraint types, such as 'as late as possible' and 'must start on', and provides examples of applying these constraints to tasks. The tutorial emphasizes the importance of limiting constraints to maintain project flexibility and efficiency. It also demonstrates how to manage constraints using different views and tools within a project management software.

Read more

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the default constraint applied to every task in a project?

Start as soon as possible

Finish no earlier than

Finish no later than

Must start on

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which constraint type would you use if a task must be completed by a specific date?

Start no earlier than

Must start on

Finish no later than

Start as soon as possible

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In the example provided, why was the 'start no earlier than' constraint applied to task #58?

To ensure the task starts immediately

To prevent the task from starting too late

To delay the task until a sale on flights

To finish the task as soon as possible

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What icon indicates that a constraint has been applied to a task?

A warning icon

A clock icon

A checkmark icon

A calendar icon

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why is it important to limit the number of constraints in a project?

To ensure all tasks start immediately

To maintain a smooth project flow

To increase the number of tasks

To reduce project flexibility

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How can you apply constraints if the task details form is not open?

By using the quick access toolbar

By using the task ribbon and information button

By clicking on the project timeline

By opening the project settings

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What happens if you select a summary task when setting constraints?

You can only set 'must start on' constraints

You cannot set any constraints

You see a limited set of constraint options

You see all constraint options