Microsoft Project 2021 From Beginners to Advanced - Exercise 03-2

Microsoft Project 2021 From Beginners to Advanced - Exercise 03-2

Assessment

Interactive Video

Information Technology (IT), Architecture

University

Hard

Created by

Quizizz Content

FREE Resource

This video tutorial guides viewers through creating a custom field in a project to flag tasks with a finish variance of five days or more. It explains how to use a flag field to identify these tasks and apply graphical indicators in a Gantt chart. The tutorial emphasizes understanding that durations are stored in minutes and provides a solution demonstration for the exercise.

Read more

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the main focus of the exercise introduced in the video?

Creating a new project from scratch

Assigning resources to tasks

Identifying tasks with a finish variance

Completing the project schedule

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How should tasks with a finish variance of five days or more be flagged?

By assigning them to a different project

By creating a custom field of type flag

By changing their color

By deleting them from the schedule

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What type of data does a flag field represent?

Text descriptions

Date and time

Numeric values

Yes/No values

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Project 2021, how are durations stored?

In minutes

In days

In weeks

In hours

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What visual indicator is used to show tasks with a significant finish variance in the project file?

A yellow triangle

A red diamond icon

A blue circle

A green checkmark