Microsoft Project 2021 From Beginners to Advanced - Exercise 05-1

Microsoft Project 2021 From Beginners to Advanced - Exercise 05-1

Assessment

Interactive Video

Information Technology (IT), Architecture

University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial guides viewers through managing task dependencies using a spreadsheet. It covers identifying predecessors, adding lag and lead time, and filtering tasks to display milestones. The tutorial provides practical examples and encourages viewers to experiment with these features to enhance their project management skills.

Read more

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of the predecessors column in a project management spreadsheet?

To show the budget for each task

To indicate which tasks are linked together

To list all tasks in the project

To display the start and end dates of tasks

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How can you visually identify linked tasks in a Gantt chart?

By the color of the bars

By the length of the bars

By arrows connecting the bars

By the position of the bars

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What happens when you add lag time to a task?

The task is moved earlier in the schedule

The task is split into multiple parts

The task is completed faster

The task is delayed by the specified number of days

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How is lead time represented when adjusting task schedules?

As a percentage

As a zero value

As a negative number

As a positive number

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which filter can be used to display only milestone tasks in a project schedule?

Resource filter

Priority filter

Milestone filter

Task duration filter