PMI-RMP Certification Training - Residual and Secondary Risk, and Risk Register Updates
Interactive Video
•
Information Technology (IT), Architecture
•
University
•
Practice Problem
•
Hard
Wayground Content
FREE Resource
Read more
5 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What should be done if residual risk is above the risk tolerance level?
Enact another risk response strategy
Increase the risk tolerance level
Ignore the risk and proceed with the project
Cancel the project
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is a recommended action if a threat risk remains above tolerance after a response?
Reduce the project's scope
Increase the project's budget
Provide a contingency plan
Ignore the risk
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Why is it important to update the risk register after developing risk response plans?
To ensure all team members are aware of the project timeline
To increase the project's budget
To finalize the project scope
To document detailed information about responses and strategies
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What are secondary risks?
Risks that are eliminated after implementing a strategy
Risks that arise from implementing a risk response strategy
Risks that are ignored during the planning phase
Risks that have no impact on the project
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What should be included in the risk register update regarding secondary risks?
The project's completion date
Newly identified risks and responsible team members
The project's financial details
Only the names of the team members
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?