What is a Linear Responsibility Chart (LRC)? PM in Under 5

What is a Linear Responsibility Chart (LRC)? PM in Under 5

Assessment

Interactive Video

Business

12th Grade - University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial explains the Linear Responsibility Chart (LRCA), a project management tool that links tasks to resources, particularly individuals. It describes the chart's structure, roles, and symbols, and highlights its benefits, such as team clarity, task specification, and communication ease. The LRCA's flexibility in adding resources and roles, and its use in budget estimation, are also discussed.

Read more

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of a Linear Responsibility Chart?

To assign roles and responsibilities to resources

To list all project tasks in a timeline

To calculate the total project cost

To track project milestones

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How does a Linear Responsibility Chart differ from a RACI chart?

It includes a timeline for tasks

It uses a different color scheme

It does not assign roles

It arranges information in a grid format

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT a benefit of using a Linear Responsibility Chart?

Monitoring multiple projects

Complex technology requirement

Flexibility in adding resources

Easy communication of roles

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What makes Linear Responsibility Charts flexible in terms of roles?

They do not use symbols for roles

They allow adding as many roles as needed

They only include supervisory roles

They use a fixed set of roles

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is required to create a Linear Responsibility Chart?

Complex software

A flip chart and a pen

A project timeline

A detailed budget

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a key feature of Linear Responsibility Charts in terms of project detail?

They only show high-level tasks

They require a fixed number of tasks

They exclude non-human resources

They can detail every single activity or group tasks

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How can Linear Responsibility Charts assist in budget estimation?

By listing all project tasks

By assigning unit costs to resources

By tracking project timelines

By providing a communication platform