What is Resource Levelling? And how does it differ from Resource Smoothing?

What is Resource Levelling? And how does it differ from Resource Smoothing?

Assessment

Interactive Video

Business, Information Technology (IT), Architecture

12th Grade - University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial explains resource levelling and resource smoothing in project management. Resource levelling addresses resourcing conflicts by adjusting project schedules or reallocating resources, while resource smoothing balances workload peaks and troughs. The tutorial discusses methods for levelling resources, such as delaying tasks or adding skilled personnel, and compares manual and automated approaches. It highlights the importance of understanding team skills and task requirements for effective resource management.

Read more

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary goal of resource leveling in project management?

To shorten project duration

To reduce project costs

To resolve resource conflicts by fair allocation

To increase the number of resources

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is a strategy used in resource leveling?

Reducing project scope

Hiring more managers

Delaying start times of tasks

Increasing project budget

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How does resource smoothing differ from resource leveling?

It increases the number of resources

It shortens project duration

It reduces project costs

It focuses on balancing workload over time

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a key characteristic of resource smoothing?

Increasing project budget

Managing time constraints

Hiring more managers

Reducing project scope

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a disadvantage of using automated algorithms for resource management?

They are always accurate

They require clearly defined skills and tasks

They are cost-effective

They reduce project duration

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When is manual resource leveling more suitable?

When project costs need to be reduced

For projects with a short duration

When skills and tasks are complex and not easily articulated

For large projects with many resources

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a requirement for using algorithmic resource leveling?

A small number of resources

A short project timeline

A large project budget

Clearly defined skills for each task