What is the primary difference between Estimate at Completion (EAC) and Budget at Completion (BAC)?
EAC: What is Estimate at Completion?

Interactive Video
•
Business
•
12th Grade - University
•
Hard
Quizizz Content
FREE Resource
Read more
7 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
EAC is always higher than BAC.
EAC includes only labor costs, while BAC includes all costs.
EAC is the expected total cost at project completion, while BAC is the initial budget estimate.
EAC is calculated before the project starts, while BAC is calculated during the project.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In the first method of calculating Estimate to Complete (ETC), what assumption is made about past problems?
Past problems will worsen over time.
Past problems are irrelevant to future work.
Past problems will continue to affect future work.
Past problems have been resolved and future work will follow the original plan.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the Cost Performance Index (CPI) used for in Earned Value Management?
To calculate the initial budget.
To adjust the Estimate to Complete based on past cost performance.
To determine the schedule performance.
To calculate the total project cost.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How is the Estimate at Completion (EAC) adjusted using the Cost Performance Index (CPI)?
EAC is multiplied by the CPI.
EAC is divided by the CPI.
EAC is added to the CPI.
EAC is subtracted from the CPI.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What additional factor is considered in the most sophisticated method of calculating EAC?
Project duration
Schedule Performance Index (SPI)
Labor costs
Material costs
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Why might it be necessary to create a new Estimate to Complete (ETC) from scratch?
Because the budget was reduced.
Because the project manager changed.
Because past assumptions may no longer be valid.
Because the project scope has increased.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the main reason for having multiple methods to calculate EAC and ETC?
To confuse project managers.
To account for different assumptions about project performance.
To ensure all projects have the same cost.
To make project management more complex.
Similar Resources on Quizizz
6 questions
China's Producer Price Gains Moderate

Interactive video
•
University
2 questions
EAC: What is Estimate at Completion?

Interactive video
•
12th Grade - University
8 questions
What is Earned Value Management - EVM? PM in Under 5

Interactive video
•
12th Grade - University
4 questions
What is Earned Value Management - EVM? PM in Under 5

Interactive video
•
12th Grade - University
6 questions
First Quarter Earnings Off to Strong Start for S&P Companies

Interactive video
•
University
8 questions
PMP Certification Training - Project Cost Management

Interactive video
•
University
2 questions
PMP Certification Training - Project Cost Management

Interactive video
•
University
6 questions
Layoffs Will Turn Morgan Stanley Bullish: Mike Wilson

Interactive video
•
University
Popular Resources on Quizizz
10 questions
Chains by Laurie Halse Anderson Chapters 1-3 Quiz

Quiz
•
6th Grade
20 questions
math review

Quiz
•
4th Grade
15 questions
Character Analysis

Quiz
•
4th Grade
12 questions
Multiplying Fractions

Quiz
•
6th Grade
30 questions
Biology Regents Review #1

Quiz
•
9th Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
50 questions
Biology Regents Review: Structure & Function

Quiz
•
9th - 12th Grade
Discover more resources for Business
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
50 questions
Biology Regents Review: Structure & Function

Quiz
•
9th - 12th Grade
20 questions
Taxes

Quiz
•
9th - 12th Grade
20 questions
Chapter 3 - Making a Good Impression

Quiz
•
9th - 12th Grade
14 questions
Attributes of Linear Functions

Quiz
•
9th - 12th Grade
10 questions
Identifying equations

Quiz
•
KG - University
50 questions
Biology Regents Review 2: Ecology

Quiz
•
9th - 12th Grade
20 questions
Investing

Quiz
•
9th - 12th Grade