Constructing Network Analysis Diagrams for Business Projects: An Example with Samsung

Constructing Network Analysis Diagrams for Business Projects: An Example with Samsung

Assessment

Interactive Video

Business

University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial explains how to construct network analysis diagrams using Samsung's TV launch as an example. It covers identifying and sequencing tasks, constructing the network diagram with activity nodes and arrows, and calculating the earliest start and latest finish times for activities. The tutorial emphasizes the importance of maintaining efficiency and setting deadlines to ensure timely project completion.

Read more

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the first step in constructing a network analysis diagram for a new product launch?

Hiring new staff

Setting a budget

Identifying tasks and activities

Identifying the target market

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why is the 'preceded by' column important in network analysis diagrams?

It lists the team members responsible

It provides the estimated time for each task

It shows the cost of each task

It identifies the order of task completion

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a key rule regarding activity arrows in network analysis diagrams?

They must connect to multiple nodes

They must intersect each other

They should be labeled with the task name

They should be drawn from right to left

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT a component of an activity node in a network analysis diagram?

Activity number

Resource allocation

Earliest start time

Latest finish time

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which activity can start immediately once the project begins in the Samsung TV example?

Designing the packaging

Assembling the final product

Negotiating with retailers

Printing the packaging

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does the earliest start time (EST) indicate in a network analysis diagram?

The cost associated with each task

The latest possible start date for a task

The earliest date a task can begin

The total duration of the project

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In the context of network analysis diagrams, what is the significance of the latest finish time (LFT)?

It identifies the team responsible for each task

It determines the earliest a task can start

It sets deadlines for task completion

It calculates the total project cost

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?