Agile Masterclass: Agile for Project Management - Other Issues
Interactive Video
•
Information Technology (IT), Architecture
•
University
•
Practice Problem
•
Hard
Wayground Content
FREE Resource
Read more
5 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is a suggested method to manage external dependencies on a Kanban board?
Ignore them and focus on internal tasks
Add a separate column to track them
Assign them to a single team member
Limit the number of dependencies
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Why is it important to create tasks for non-product related activities on the Kanban board?
To ensure they are visible and managed efficiently
To reduce the workload of the team
To increase the number of tasks on the board
To eliminate the need for follow-ups
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How can improvement tasks be effectively managed on a Kanban board?
By assigning them to a separate team
By ignoring them until the product is complete
By adding them to the board for visibility
By setting a strict deadline for each task
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is a benefit of assigning a new hire to the slowest step of the process?
It helps the new hire learn faster
It increases the output of the process
It reduces the workload of other team members
It speeds up the entire workflow
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the main purpose of customizing a Kanban board according to the lecture?
To make it visually appealing
To reflect all tasks done by the team
To reduce the number of tasks
To focus only on product-related work
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?