Risk Management 101 for IT Professionals Essential Concepts - Sample Risk Assessments

Risk Management 101 for IT Professionals Essential Concepts - Sample Risk Assessments

Assessment

Interactive Video

Information Technology (IT), Architecture, Business

University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial covers three risk assessment scenarios, focusing on both qualitative and quantitative methods. The first scenario involves a project manager dealing with schedule delays in an IT modernization project. The second scenario examines the impact of COVID-19 on VPN stability and employee productivity. The final scenario uses quantitative analysis to assess the risk of an aging air conditioning system in a server room, determining the cost-effectiveness of replacing it.

Read more

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In the first qualitative risk assessment scenario, what is the main reason for the project being behind schedule?

Technical integration issues

Poor project management

Lack of resources

Budget constraints

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the current level of schedule risk in the first scenario?

Critical

Low

High

Moderate

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In the second scenario, what is the primary issue affecting employee productivity?

Inadequate hardware

VPN disconnections

Poor management

Lack of training

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How is the risk score determined in the second qualitative risk assessment scenario?

By adding impact and probability

By subtracting probability from impact

By multiplying impact and probability

By dividing impact by probability

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In the quantitative risk assessment scenario, what is the expected cost of lost sales if the AC system fails?

$20,000

$10,000

$25,000

$5,000

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the annualized loss expectancy calculated in the quantitative risk assessment?

$6,600

$3,300

$9,900

$12,000

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why is it recommended to replace the AC unit in the quantitative risk assessment scenario?

To improve energy efficiency

To prevent server downtime and save costs

To comply with regulations

To upgrade to a newer model