PMI-RMP Certification Training - Risk-Related Contract Decisions and Project Management

PMI-RMP Certification Training - Risk-Related Contract Decisions and Project Management

Assessment

Interactive Video

Information Technology (IT), Architecture, Business

University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial discusses the importance of risk response in project management, focusing on how it affects contract selection and necessitates updates to the project management plan and documents. It provides guidelines for creating a risk response plan, including identifying risks, choosing effective strategies, and developing contingency plans. The tutorial emphasizes the integration of risk response plans into the overall project management plan and concludes with reflective questions on the significance of these efforts in the project lifecycle.

Read more

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary focus when selecting a contract type in relation to risk?

Project duration

Cost minimization

Risk transference

Stakeholder satisfaction

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT typically updated in the project management plan due to risk response strategies?

Project schedule

Resource allocation

Marketing strategy

Work breakdown structure

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why is it important to update project documents like the assumptions log?

To ensure all team members are aware of changes

To increase project costs

To reduce the number of stakeholders

To delay project timelines

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the first step in creating a risk response plan?

Examining each identified risk

Allocating resources

Identifying backup strategies

Developing contingency plans

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What should be included in a contingency plan?

Cost and schedule reserves

Marketing strategies

Stakeholder feedback

Project milestones

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When should a contingency plan be enacted?

When the budget is approved

When the project starts

When the risk trigger occurs

When the project ends

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of consulting the risk management plan when creating a risk response plan?

To determine the project's marketing strategy

To select project team members

To understand the content and format of the risk response plan

To finalize the project budget