Agile Scrum Master Certification Exam Prep (CSM) - Release Phase
Interactive Video
•
Information Technology (IT), Architecture, Business
•
University
•
Practice Problem
•
Hard
Wayground Content
FREE Resource
Read more
5 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the primary focus of the final phase in the Scrum process?
Delivering planned deliverables
Planning new deliverables
Canceling incomplete tasks
Reassigning team roles
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Who is responsible for documenting accepted deliverables in the Scrum process?
Scrum Master
Product Owner
Stakeholders
Scrum Team
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the main purpose of the project retrospective in Scrum?
To assign new tasks
To finalize project budget
To celebrate project completion
To review project results and learn lessons
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which team members are involved in the project retrospective?
Stakeholders and the Scrum core team
Only the Product Owner
Only the Scrum Master
External consultants
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How are lessons learned from the retrospective process used in future projects?
They are used to reduce team size
They are shared with competitors
They are documented and implemented
They are ignored
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?