Microsoft Project 2021 From Beginners to Advanced - Inactive Tasks
Interactive Video
•
Information Technology (IT), Architecture
•
University
•
Practice Problem
•
Hard
Wayground Content
FREE Resource
Read more
5 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the purpose of switching to the summary view when dealing with inactive tasks?
To delete unnecessary tasks
To view the project summary task and summary tasks
To increase project costs
To hide completed tasks
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following details can be seen in the summary task view?
Only the total project cost
Only task names
Only start and finish dates
Task names, durations, start and finish dates, percentage complete, cost, and work hours
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the total project cost mentioned in the video before any tasks are made inactive?
$17,566
$4,480
$1,496
$22,046
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Why might you choose to make a task inactive instead of deleting it?
To permanently remove it from the schedule
To keep it in the schedule without affecting costs or duration
To increase the project duration
To hide it from the summary view
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How can you reactivate a task that was previously made inactive?
By untoggling 'Inactivate' in the task tab
By deleting it and adding it again
By clicking the 'Delete' button
By changing the project summary task
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?