Microsoft Project 2021 From Beginners to Advanced - Fixed Task Costs

Interactive Video
•
Information Technology (IT), Architecture
•
University
•
Hard
Quizizz Content
FREE Resource
Read more
7 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is a fixed task cost in project management?
A cost that is only applicable to material resources
A cost that varies with the amount of resources used
A cost associated with a specific task that does not change
A cost that is calculated based on the project's total budget
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which column in the cost table is used to enter a fixed task cost?
Variance
Total Cost Baseline
Fixed Cost
Fixed Cost Accrual
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does the 'start' option in fixed cost accrual method signify?
The cost is accrued at the end of the task
The cost is not accrued at all
The cost is accrued at the start of the task
The cost is accrued evenly throughout the task
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How can you document multiple fixed costs for a single task?
By using a spreadsheet outside the project management tool
By creating a separate task for each cost
By adding a note in the task's information section
By assigning each cost to a different resource
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the importance of adding notes for fixed costs?
To ensure everyone is aware of the cost breakdown
To increase the total project cost
To reduce the number of tasks in the project
To make the project appear more complex
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How is a consultant's fixed cost typically handled in project management?
By ignoring it in the cost table
By including it in the material costs
By setting an hourly rate
By assigning a cost per use
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the total cost of a task if it has a fixed cost of $2000 and additional resource costs of $1200?
$3200
$4000
$1200
$2000
Similar Resources on Wayground
2 questions
Planning and Control Using Microsoft Project 365 and 2021 - Workshop 16 - Assigning Resources to Tasks

Interactive video
•
University
8 questions
Microsoft Project 2021 From Beginners to Advanced - Overtime

Interactive video
•
University
8 questions
Microsoft Project 2021 From Beginners to Advanced - Outline Codes

Interactive video
•
University
3 questions
Microsoft Project 2021 From Beginners to Advanced - Exercise 09-1

Interactive video
•
University
4 questions
Microsoft Project 2021 From Beginners to Advanced - Cost Rates and Rate Changes

Interactive video
•
University
6 questions
PMP Certification Training - Overview of Project Cost Management and Processes

Interactive video
•
University
4 questions
Microsoft Project 2021 From Beginners to Advanced - Cost Accrual

Interactive video
•
University
6 questions
Microsoft Project 2021 From Beginners to Advanced - Create a Cost Resource

Interactive video
•
University
Popular Resources on Wayground
50 questions
Trivia 7/25

Quiz
•
12th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
11 questions
Negative Exponents

Quiz
•
7th - 8th Grade
12 questions
Exponent Expressions

Quiz
•
6th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade
20 questions
One Step Equations All Operations

Quiz
•
6th - 7th Grade
18 questions
"A Quilt of a Country"

Quiz
•
9th Grade