Microsoft Project 2021 From Beginners to Advanced - Resource Overallocations

Interactive Video
•
Information Technology (IT), Architecture
•
University
•
Hard
Quizizz Content
FREE Resource
Read more
7 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What issue arises when a task is reassigned to the IT trainer?
The task is marked as unimportant.
The task is automatically deleted.
The task is completed ahead of schedule.
The task causes an over-allocation of time.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Why is it advised not to use the 'Prevent Over Allocations' button?
It permanently deletes tasks.
It increases the workload of the trainer.
It does not affect the schedule at all.
It can cause unexpected changes without notifying the user.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does the red person icon in the Gantt chart view indicate?
A task is under budget.
A task has over-allocated resources.
A task is on hold.
A task is completed.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the purpose of the 'Scroll to Task' button in the Gantt chart view?
To delete a task.
To jump to the relevant part of the Gantt chart for a specific task.
To add a new task.
To export the Gantt chart.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In the resource usage view, what does highlighting a resource in red signify?
The resource is underutilized.
The resource is over-allocated.
The resource is on vacation.
The resource is not assigned any tasks.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is a potential solution for resolving over-allocations?
Reducing the number of resources available.
Assigning additional resources to the tasks.
Ignoring the over-allocation warning.
Assigning more tasks to the same resource.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How can filtering help in managing over-allocations?
By hiding all tasks.
By showing only over-allocated resources.
By increasing the workload of all resources.
By deleting over-allocated tasks.
Similar Resources on Wayground
6 questions
Microsoft Project 2021 From Beginners to Advanced - Create a Cost Resource

Interactive video
•
University
6 questions
Microsoft Project 2021 From Beginners to Advanced - What's New in Project 2021?

Interactive video
•
University
6 questions
Planning and Control Using Microsoft Project 365 and 2021 - Workshop 17 - Resource Graphs and Tables

Interactive video
•
University
2 questions
Microsoft Project 2021 From Beginners to Advanced - Exercise 09-1

Interactive video
•
University
6 questions
Microsoft Project 2021 From Beginners to Advanced - Use Task Inspector to Identify Issues

Interactive video
•
University
8 questions
Planning and Control Using Microsoft Project 365 and 2021 - Workshop 16 - Assigning Resources to Tasks

Interactive video
•
University
4 questions
Microsoft Project 2021 From Beginners to Advanced - Advanced Resource Sharing and Resource Pools

Interactive video
•
University
6 questions
Microsoft Project 2021 From Beginners to Advanced - Create a Cost Resource

Interactive video
•
University
Popular Resources on Wayground
50 questions
Trivia 7/25

Quiz
•
12th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
11 questions
Negative Exponents

Quiz
•
7th - 8th Grade
12 questions
Exponent Expressions

Quiz
•
6th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade
20 questions
One Step Equations All Operations

Quiz
•
6th - 7th Grade
18 questions
"A Quilt of a Country"

Quiz
•
9th Grade