1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In approximate estimates, what is the total cost worked out in the prescribed form referred to as?

Detailed Estimate

Abstract of Estimated Form

Quantity Survey

Bill of Quantities

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What percentage of the estimated cost is typically allocated for Petty Supervision and contingencies items in approximate estimates?

2%

3%

4%

5%

3.

MULTIPLE CHOICE QUESTION

30 sec • Ungraded

Are you enjoying the video lesson?

Yes

No

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following are examples of items of work divided in a detailed estimate?

Earth work

Concreting

Brick work and R.C.C. Plastering

All of the above

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How are quantities calculated in a detailed estimate form?

By adding length and breadth

By multiplying values in the numbers column to the Depth column

By subtracting depth from length

By dividing breadth by height

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?